Choosing water main replacement projects that benefit our community

Label: Blog post
The Portland Water Bureau proactively replaces aging water mains to keep our drinking water system reliable and resilient. We consider many factors when choosing which mains our crews will replace. These projects reduce the risk of breaks and avoid costly repairs in the future.
Published

Below your feet lies a network of water mains, or pipes, that carries drinking water from storage tanks and reservoirs to taps around town. Portland's drinking water system has more than 2,250 miles of pipe doing the invisible work of keeping the region hydrated every single day.

Portland's water system is large and includes over 2,250 miles of pipe, many of which are very old.

Many of these pipes are very old—almost a quarter were installed before 1930! As pipes age, they become much more likely to leak or break. Replacing pipes before they fail keeps water service reliable, keeps our system resilient, and avoids more costly repairs in the future.

On average, Portland Water Bureau crews proactively replace around 30,000 feet of water main each year. That's a lot of pipe! But it's only a fraction of the aging pipes in our drinking water system. We can't replace them all at once. So how do we decide which water mains to replace first?

Setting the target

Most years, our crews replace around 30,000 feet of water main.

Before we can decide which pipes to replace each year, we need to decide how much pipe we can replace.

Ahead of every fiscal year, teams from our engineering group and maintenance and construction group look at the budget and our crews' work capacity. Together, they decide how many linear feet of water main we can replace during the upcoming year.

Narrowing down the list

Once we've determined how many feet of water main we can replace for the year, it's time to choose which mains to replace. Because we have so many aging water mains, we need to narrow down the number of potential projects.

As you might imagine, it would take a very long time for staff to consider every water main and determine whether it's a good candidate for replacement. That's where technology comes in! We have geographic information system (GIS) models that help us filter out some pipes and project areas. Then a machine learning model uses our robust system data to narrow the list of potential projects even more.

Once we have a list of the top 200 to 250 projects to choose from, staff use their real-world experiences and expertise to put together a final list of 60 to 70 projects for the year.

What we look for in a main replacement project

We start by looking for mains that are most at-risk of failing or that don't meet our current design standards. (For example, mains with a diameter of less than four inches no longer meet our design standards. We want to replace them with larger pipes when possible.)

When pipes near the end of their useful lives, they become more likely to leak or break, like the pipe pictured here. We try to replace pipes before they reach this point.

When choosing mains for replacement, we consider many factors, including:

  • A main's history of leaks or breaks
  • Observations and recommendations from field crews
  • A pipe's age
  • What a pipe is made of (some pipe materials last longer than others)
  • A pipe's size

While age is one factor we consider, the oldest pipes aren't always the most likely to fail! For example, pipes from the early 1900s are made of thick cast iron that tends to last a long time. Cast iron pipes from the 1950s and 1960s were made differently, so they're much thinner and more likely to break. We use data about pipe failures to estimate how long different kinds of pipes are likely to last so we can replace them before they fail.

We also look at other City work that might be happening in the street. For example, if the Portland Bureau of Transportation plans to repave a road, we'll try to replace the water main first so we don't disturb the new road surface. Aligning our projects can save our customers from dealing with long or frequent construction.

But looking at a main's physical characteristics and nearby projects is just part of how we plan this work. We also consider the Social Vulnerability Index (SVI) rankings of the potential project locations. SVI looks at 16 factors, which fall under four themes:

  • Socioeconomic status
  • Household characteristics, like age and disability
  • Racial and ethnic minority status
  • Housing type and transportation

SVI helps us estimate how difficult it would be for Portlanders to deal with a broken water main. We prioritize main replacements in areas of high social vulnerability.

Projects that aren't a good fit

We also look at factors that could mean a water main isn't a good candidate for replacement by Water Bureau crews right now. A potential project may be removed from the list if it has poor pavement conditions, is under a road that requires a special permit to cut into, or is too close to other recent projects. We may bump a project down the list if rights-of-way and easements could make work challenging or if a project would need extra work, like upgrading meter connections.

Project size is another limiting factor. We typically don't do projects that replace more than about 600 to 800 feet of main using our own crews. Proactive main replacement work is just one of many things our field staff do to keep water flowing. Crews also do other maintenance work, install water service lines for new buildings, and respond to emergencies.

If a project isn't a good fit for our own crews to complete, we may plan and design it as a project for contractors instead.

Turning selection into action

Before our field crews can begin work, many other Water Bureau teams must complete important steps to ensure the project is successful. Surveyors, pictured here, do some of this important prep work, including taking detailed measurements of project sites.

By July 1 (the start of the City's fiscal year), the Water Bureau has usually selected 60 to 70 main replacement projects for the new fiscal year. For fiscal year 2026–27, we have 64 water main replacement projects planned for our crews.

Once we've selected the final projects for the year, many more Water Bureau teams begin their parts of the process. Staff work to get the necessary permits, survey the project sites, design the projects, and plan for any necessary operational changes. Only then can our maintenance and construction crews get started on the project's construction work.

These projects have a big payoff for Portlanders. Proactive maintenance is a critical piece of our commitment to serving excellent water every minute of every day. Regularly replacing mains keeps our water system more reliable and reduces the number of big breaks we experience.

Main replacements are usually our biggest and longest maintenance projects. We plan ahead so we can perform work more efficiently, minimize impacts on our community, and keep project costs as low as possible. And we do our best to communicate with affected homes and businesses before we begin work so folks know what to expect during construction.

Learn more about what to expect if we are replacing a water main near you

Learn more about how we maintain Portland's drinking water system