Willamette River Crossing Project Update - February 2021

News Article
Bridge looking over the Willamette with pipes illistated below the water and soil is visible.
Published
  • In August 2020, we finished work with our geotechnical probe, or geoprobe. The team is now using results from that probe to plan the next phase of the project.
  • Crews are working during times of year approved by the Oregon Department of Fish and Wildlife. We don’t expect any impacts to fish and wildlife or recreational uses from this work. 
  • Crews will collect soil samples then fill holes and restore each area to its previous condition. This will help us gather more information about soil deep underground.

Project Update February 2021