Willamette River Crossing Project Update - January 2020

News Article
Bridge looking over the Willamette with pipes illistated below the water and soil is visible.
Published
a tugboat leaves dock on the willamette river with a purple sunset
  • Come hear our project overview and briefing at February’s Downtown Neighborhood Association meeting. This is an ADA-accessible facility.
  • Will be upcoming traffic updates.
  • Here’s a quick recap of developments so far:
    • This project will place a water main deep under the Willamette River for earthquake protection, instead of the current crossings with water pipes on bridges.
    • We’ll use a geotechnical probe to establish the underground path for the water main.
    • We’ve done advance soil sampling to help guide the probe.
    • Both the probe and the water main installation will start on the west side of the river and proceed to the east side.

Project Update January 2020

Contact

WRX Project Team

phone number503-823-7499Project Voicemail/Hotline - Press zero at any time to skip the message and leave a voicemail. Please leave your name and phone number twice. A staff person will call you within one to three business days. To report a water service emergency, call 503-823-4874.
Oregon Relay Service711Oregon Relay Service

Katy Asher

Senior Communications Specialist
phone number503-865-60548 a.m. to 5 p.m. Monday through Friday
Oregon Relay Service711Oregon Relay Service