Read the Jan. 24, 2025 Bull Run Treatment Project Construction Activity Update to learn about construction activity for the week beginning Jan. 27.
Published
- Work in the Lusted Road/Altman Road intersection to install new Pleasant Home Water District (PHWD) water lines is nearly complete. The intersection is expected to be closed Monday January 27 during shift hours while this work is finished.
- Crews will also be working on service installation, testing and commissioning of the new PHWD water lines in Lusted Road between the intertie site and the Altman Road intersection. The traffic restrictions on Lusted Road between Hosner Road and Altman Road will continue for a few more weeks while this work is happening.
- We also expect the westbound lane closure on Oxbow Drive near the Altman Road intersection to continue into February. There will be flaggers at the intersection to direct traffic starting Saturday, January 25.
- Note: Temporary full closure of Pipeline Road near the intersection with Altman Road is expected February 3-7. Through traffic will be detoured. Local and emergency access will be maintained. Additional information will be shared as available.