Please read the Sept. 7, 2024 Bull Run Treatment Project Construction Activity Update.
Published
- Crews are working on the south side of Lusted Road, east of the Altman intersection, to help prepare for upcoming pipeline construction. This includes clearing, grubbing, and preparing to widen the road within the existing public right-of-way to help accommodate traffic during pipeline construction.
- Finishing work will continue along parts of Lusted Road, Altman Road, and Hosner Road including installing shoulder rock and striping.
- Work to improve the Carpenter Lane access to the filtration facility site is ongoing, including paving the road and the temporary pedestrian path on Carpenter Lane and installing retaining wall and right turn lane at Dodge Park Boulevard and Cottrell Road.