Filtration Neighbor Update - July 30, 2024

Newsletter
Please read the July 26, 2024 Bull Run Treatment Project Construction Activity Update.
Published

 

Exploratory excavations using a vacuum truck to locate utilities and other work along parts of Carpenter Lane, Cottrell Road, and Dodge Park Boulevard will continue the week of July 29. This work is needed to prepare for updating these roads to Multnomah County roadway standards, including widening the pavement, resurfacing the asphalt, and adding a gravel shoulder. 

Crews will also start construction at the raw water/tunnel site off Lusted Road near the Clackamas/Multnomah county line the week of July 29.

Read the Construction Activity Update 