Please read the Oct. 4, 2024 Bull Run Treatment Project Construction Activity Update.
Published
- Crews are beginning work to widen the east side of Altman Road, between Pipeline Road and Lusted Road, within the public right-of-way. This will help with traffic management during upcoming pipeline construction, including installation of new Pleasant Home Water District water mains later this year.
- Work continues to improve the facility site access on Cottrell Road between Carpenter Lane and Dodge Park Boulevard. Paving of this part of Cottrell is planned over two Saturdays (“first lift” paving on Oct. 5 and “top lift” paving on Oct. 12), followed by shoulder work and hydroseeding.
- With the improvements to the Carpenter Lane facility access wrapping up, contractors are now ready to start off-hauling stockpiled clean soils from the site.