Read the July 2, 2026 Bull Run Filtration construction activity update to learn about work happening the week of July 6, 2026.
Published
- No project construction activities are planned Friday July 3 or Saturday July 4 in observance of Independence Day.
- Current traffic impacts
- Lusted Road (between Altman Road and west of Hosner Road) through July 15, 2026: Local access only closure with one-way eastbound traffic outside work hours. Through traffic will be detoured to Altman Road or Hosner Road. Residents within the work zone on Lusted Road will have access from the west.
- Lusted Road (just north of county line) through October 17, 2026: Closure during work hours with two-way traffic managed by temporary traffic signals outside work hours. During work hours, residents will be able to travel either north or south of the closure. Through traffic will be detoured to Dodge Park Boulevard and Cottrell Road.
- Controlled blasts during pipeline shaft excavation scheduled activities: No blasts currently scheduled
- Other work happening the week of July 6
- Upcoming traffic impacts
- Upcoming meetings: July neighbor update meeting and coffee with the contractor