Read the July 17, 2026 Bull Run Filtration construction activity update to learn about work happening the week of July 20, 2026.
Published
- Current traffic impacts
- Lusted Road (just north of county line) through October 17, 2026: Closure during work hours with two-way traffic managed by temporary traffic signals outside work hours. During work hours, residents will be able to travel either north or south of the closure. Through traffic will be detoured to Dodge Park Boulevard and Cottrell Road.
- Note July 13-24 the City of Sandy will be repaving Bluff Road, between Proctor and Hudson roads, where a new water pipeline was recently installed in the right-of-way that will help connect their existing water system to the filtration facility. Visit the City of Sandy project webpage for more information.
- Controlled blasts during pipeline shaft excavation scheduled activities: No blasts currently scheduled
- Other work happening the week of July 20
- Upcoming traffic impacts