Filtration Neighbor Update - May 15, 2026

Label: Newsletter
Read the May 15, 2026 Bull Run Filtration construction activity update to learn about work happening the week of May 18, 2026.
Published

 

  • Current traffic impacts
    1. Lusted Road (between Altman Road and west of Hosner Road) through June 15, 2026: Local access only closure with one-way eastbound traffic outside work hours. Through traffic will be detoured to Altman Road or Hosner Road. Residents within the work zone on Lusted Road will have access from the west. 
    2. Lusted Road (just north of county line) through July 15, 2026: Closure during work hours with two-way traffic managed by temporary traffic signals outside work hours. During work hours, residents will be able to travel either north or south of the closure. Through traffic will be detoured to Dodge Park Boulevard and Cottrell Road. Access for school buses and emergency vehicles will be maintained.
  • Controlled blasts during pipeline shaft excavation scheduled activities: May 18, 2026 between 12 p.m. and 4 p.m. (tentative)
  • Other work happening the week of May 18
  • Upcoming traffic impacts
  • Upcoming coffee with the contractor

Read the activity update

Back to top