Read the March 6, 2026 Bull Run Filtration construction activity update to learn about work happening the week of March 9.
Published
- Current traffic impacts
- Lusted Road (between Altman Road and west of Hosner Road) through May 23, 2026: Local access only closure with one-way eastbound traffic outside work hours. Through traffic will be detoured to Altman Road or Hosner Road. Residents within the work zone on Lusted Road will have access from the west.
- Lusted Road (near county line) through May 23, 2026: Single-lane restriction with 24/7 temporary traffic signals to manage two-way traffic flow during installation of new water pipelines. Flagging may also be used during work hours. To address safety issues, we are working with the counties to change the traffic controls to a 24/7 full closure on Lusted Road in front of the pipeline work site entrance starting in late March. We will share more information as it becomes available. Through traffic would be detoured to Dodge Park Boulevard and Cottrell Road. Emergency vehicles and school busses would be provided alternate access.
- Note there will be restriping happening on Dodge Park Boulevard from just east of Altman Road to Cottrell Road. This work will involve a moving work zone controlled by flaggers and is expected to happen in March.
- Note the City of Sandy is installing a new water pipeline along the Bluff Road right-of-way, between Proctor and Hudson roads, that will help connect their existing water system to the filtration facility. This work is expected to be ongoing through May 1, 2026. Visit the City of Sandy project webpage for more information.
- Upcoming traffic impacts
- Other work happening the week of March 9
- Upcoming coffee with the contractor