Read the March 13, 2026 Bull Run Filtration construction activity update to learn about work happening the week of March 16.
Published
- Current traffic impacts
- Lusted Road (between Altman Road and west of Hosner Road) through May 23, 2026: Local access only closure with one-way eastbound traffic outside work hours. Through traffic will be detoured to Altman Road or Hosner Road. Residents within the work zone on Lusted Road will have access from the west.
- Lusted Road (near county line) through mid-June 2026: Single-lane restriction with 24/7 temporary traffic signals to manage two-way traffic flow during installation of new water pipelines. Flagging may also be used during work hours. To address safety issues, we are working with the counties to change the traffic controls to a 24/7 full closure on Lusted Road near the county line starting March 23. We will share more information as it becomes available. Residents will be able to travel either north or south of the closure. Through traffic will be detoured to Dodge Park Boulevard and Cottrell Road. Access for school buses and emergency vehicles will be maintained.
- Portland General Electric is doing utility work along Dodge Park Boulevard that is expected to continue through early April and may involve temporary traffic restrictions where work happening.
- The City of Sandy is installing a new water pipeline along the Bluff Road right-of-way, between Proctor and Hudson roads, that will help connect their existing water system to the filtration facility. This work is expected to be ongoing through May 1, 2026. Visit the City of Sandy project webpage for more information.
- Upcoming traffic impacts
- Other work happening the week of March 16