  • Current traffic impacts
    1. Altman Road/Lusted Road intersection through January 24, 2026: Local access only closure with one-way eastbound traffic outside work hours on Lusted Road and one-way northbound traffic outside work hours on Altman Road. Through traffic will be detoured to Oxbow Drive or Dodge Park Boulevard. Residents within the work zone on Lusted Road will have access from the west and residents within the work zone on Altman Road will have access from the north. Starting mid-week, workers will be installing temporary paving on Altman Road from the intersection to about 150 feet north.
    2. Lusted Road (near county line) through May 1, 2026: Single-lane restriction with 24/7 temporary traffic signals to manage two-way traffic flow during installation of new water pipelines. Flagging may also be used during work hours.
    3. There will also be restriping happening on Dodge Park Boulevard January 14 from just east of Altman Road to just east of Cottrell Road. This work is expected to take a half day and will involve a moving work zone controlled by flaggers.
  • Upcoming traffic impacts
  • Other work happening the week of Jan. 12
  • January 8, 2026 neighbor update meeting recap
  • Upcoming coffee with the contractor meeting

Read the activity update