Read the Aug. 8, 2025 Bull Run Treatment Project Construction Activity Update to learn about work happening the week of Aug. 11.
Published
-
Traffic impacts
- Altman Road/Pipeline Road intersection and Altman Road (between Pipeline Road and Oxbow Drive) August 14-19: Road closure 24/7 with signed detours for through and local traffic to Oxbow Drive or Lusted Road. Emergency access will be maintained.
- Altman Road (between Lusted Road and Pipeline Road) through October: Flagged traffic Monday through Saturday to install new Pleasant Home Water District water lines. Road closure Saturday August 16. Outside of shift hours, work areas will be steel plated to allow normal traffic flow. Altman/Lusted intersection will also be flagged August 13-15.
- Dodge Park Boulevard (east of Cottrell Road to east of Altman Road) through October: Flagged two-way traffic Monday through Saturday to install new water pipeline in the public right-of-way on the south side of the road. Normal traffic will resume outside of shift hours.
- Lusted Road near the county line through August 13: Flagged two-way traffic 24/7.
- Cottrell Road south of Dodge Park Boulevard: We're aware of the uneven road surface (a dip) on Cottrell Road between Dodge Park Boulevard and Bluff Road. We're working with Multnomah County to repave the road soon. Signs with lights have been added to alert drivers in the interim. Please use caution when driving through this section of the road. Cottrell Road north of Lusted Road will resume being used as a haul route.
- Other work happening the week of Aug. 11.