Read the Aug. 29, 2025 Bull Run Filtration construction activity update to learn about work happening the week of Sept. 1.
Published

 

  • Traffic impacts
    1. Altman Road (between Pipeline Road and Oxbow Drive) through end of October: Road closure Tuesday through Saturday during work hours with signed detours for through traffic to use Oxbow Drive or Lusted Road. School buses and emergency vehicles will be flagged through the work area as needed. Flaggers will provide local residents access from Lusted Road. Outside of work hours, the road will be open to one-way northbound-only traffic.
    2. Dodge Park Boulevard (east of Cottrell Road to east of Altman Road) through end of October: Flagged two-way traffic Tuesday through Saturday to install new water pipeline in the public right-of-way on the south side of the road. Normal traffic will resume outside of work hours. Note that a full closure of Dodge Park Boulevard is planned in October to allow for construction of pipeline crossings.
    3. Cottrell Road south of Dodge Park Boulevard: We're aware of the uneven road surface (a dip) on Cottrell Road between Dodge Park Boulevard and Bluff Road. We're planning to repave the road in mid-September. Signs with lights have been added to alert drivers in the interim. Please use caution when driving through this section of the road. Cottrell Road north of Lusted Road will resume being used as a haul route.
  • Other work happening the week of Sept. 1.

Read the activity update