Read the July 11, 2025 Bull Run Treatment Project Construction Activity Update to learn about work happening the week of July 14.
Published
Lusted Road (between Hosner Road and Altman Road) July 11-29: Flagged two-way traffic while crews complete testing and install services for new Pleasant Home Water District water lines.
- Dodge Park Boulevard (west of Cottrell Road) July 12: Flagged two-way traffic while crews set up equipment for clearing the public right-of-way on the south side of Dodge Park Boulevard. Traffic restrictions will be limited to Saturday, July 12 and clearing remaining items in the public right-of-way will continue throughout July.
- Pipeline Road and Altman Road Intersection July 17-21: Flagged two-way traffic while crews complete exploratory pipeline work.
- Other work happening the week of July 14