Filtration Neighbor Update - Dec. 5, 2025

Label: Newsletter
Read the Dec. 5, 2025 Bull Run Filtration construction activity update to learn about work happening the week of Dec. 8.
Published

 

  • Current traffic impacts
    1. Altman Road/Lusted Road intersection through January 24, 2026: Local access only closure with one-way eastbound traffic outside work hours on Lusted Road and one-way northbound traffic outside work hours on Altman Road. Through traffic will be detoured to Oxbow Drive or Dodge Park Boulevard. Residents within the work zone on Lusted Road will have access from the west and residents on Altman Road will have access from the north.
    2. Lusted Road (near county line) through May 1, 2026: Single-lane restriction with 24/7 temporary traffic signals to manage two-way traffic flow during installation of new water pipelines. Flagging may also be used during work hours.
  • Upcoming traffic impacts
  • Other work happening the week of Dec. 8
  • Upcoming Bull Run Filtration: coffee with the contractor

Read the activity update