Filtration Neighbor Update - Oct. 31, 2025

Newsletter
Read the Oct. 31, 2025 Bull Run Filtration construction activity update to learn about work happening the week of Nov. 3.
Published

 

  • Traffic impacts happening now
    1. Altman Road/Lusted Road intersection November 3-December 12: Local access only closure with one-way westbound traffic outside work hours on Lusted Road and one-way northbound traffic outside work hours on Altman Road. Through traffic will be detoured to Oxbow Drive or Dodge Park Boulevard. Residents on Altman Road will have access from the north and residents on Lusted Road will have access from the east. Note the Lusted Road traffic restrictions are planned to continue through May 15, 2026, during installation of new water pipelines on the north side of the right-of-way.
    2. Lusted Road (near county line) November 3-19: Single-lane restriction with two-way flagging during work hours. Normal traffic flow will resume outside work hours. Note the Lusted Road traffic restrictions are planned to continue through May 1, 2026, during installation of new water pipelines. Starting November 20, 2025, temporary traffic signals will be in place to help manage two-way traffic flow.
  • Traffic impacts coming up
  • Other work happening the week of Nov. 3
  • Upcoming Bull Run Filtration: coffee with the contractor

Read the activity update