SW Main-Taylor Sewer Project

Sewer and Stormwater
Active
Construction is expected to be completed in May.
Environmental Services has nearly completed a project to repair 10,765 feet, or two miles, of aging public sewer pipes in downtown Portland. Having provided 100 to 150 years of service, pipes require repairs to reduce risks of basement flooding and sewage releases to downtown buildings and streets.
Construction is anticipated to occur in the spring of 2024, perhaps in May..
Environmental Services will construct a sewer service lateral repair in SW Washington Street. The repair, now planned for the spring of 2024, will help prevent backups into buildings and streets.

SW Market-Madison Sewer Project

Sewer and Stormwater
Active
Construction is anticipated to begin in April or May of 2024 and take a year and a half to complete.
Environmental Services is constructing a project to repair 11,720 feet (more than two miles) of public sewer pipes in downtown Portland. Having provided up to 140 years of service, pipes require repairs to reduce the risks of basement flooding and sewage releases to downtown buildings and streets.

Lower Northwest Sewer Capacity Project

Sewer and Stormwater
Active
This project is in the design stage and is estimated to begin construction in the fall of 2025.
Environmental Services is designing a project that will upgrade public sewer and stormwater pipes and install new water quality treatment vaults in Northwest Portland. This project will protect the public and the environment by reducing street flooding and sewage releases to homes and businesses.
Design has been completed. Construction is expected to begin in April or May of 2024 and should take about six months to complete.
Environmental Services, in partnership with the Portland Water Bureau, has completed design on a project to upgrade infrastructure in NW Portland. This project will increase system capacity, reduce the risk of sewer discharges, and improve earthquake resilience for our critical infrastructure.

North Slabtown Sewer Project

Sewer and Stormwater
Active
Construction is anticipated to begin in Fall 2024 and take up to a year to complete.
Environmental Services is beginning the design stage of the North Slabtown Sewer Project. This project will repair or replace approximately 3,569 feet of aging public sewer pipes throughout your neighborhood. Taking these actions now will help protect public health and the environment.

Flanders Connector at NW Naito and Glisan

Transportation
Engineering And Design
Project schedule under development
The Flanders Connector at NW Naito and Glisan seeks to provide a new crossing for pedestrians and people biking at Naito Parkway, connecting Waterfront Park to the Flanders Greenway.