SE Cooper Street and SE 62nd Avenue Safe Routes to School Project

Label: Transportation
Label: Engineering and design
This project will fill the existing sidewalk gap on the north side of SE Cooper Street, pave SE Cooper Street from SE 62nd Avenue to existing pavement, install a new sedimentation-sump maintenance hole, and install 3 new curb ramps.
Construction to be complete by summer 2026

What's Happening Now? 

Construction is complete.

Last Updated Feb 2, 2026

Project Background

Portland Bureau of Transportation's Safe Routes to School (SRTS) program conducted outreach in 2017 with Portland Public Schools and their communities to determine future projects according to highest safety need. SE Cooper Street was identified as part of the SRTS priority network for students walking and rolling to and from Lane Middle School. You can learn more about the SRTS outreach process and see the SRTS Infrastructure Plan map here.

Project Goals

  • Build a walking path for students and families walking along SE Cooper St
  • Collect stormwater at the intersection of SE Cooper St and SE 62nd Avenue to prevent water from ponding
  • Repair SE Cooper St road conditions

Project Design

  • Sidewalk: Construct ~100 ft of concrete sidewalk on the north side of SE Cooper Street to infill the existing sidewalk gap
  • Curb Ramps: Construct 2 curb ramps on the east side of SE 62nd Avenue and one curb ramp on the west side of SE 62nd Avenue
  • Sedimentation Maintenance Hole and Sump: Partner with the Bureau of Environmental Service to install a sedimentation maintenance hole and sump at the intersection of SE 62nd Avenue and SE Cooper Street.  The improvements will reduce the risk of combined sewer overflows and prevent flooding by collecting and infiltrating stormwater runoff. To learn more about the impact and function of the sump system, visit Environmental Services Portland's Underground Injection Control (UIC) Facilities Stormwater Permit webpage.
  • Road repair: Pave SE Cooper Street from SE 62nd Avenue to tie into existing repaired roadway 100 feet east.

Project Schedule

  • Project Development: March - July 2024
  • Survey: August- September 2024
  • Preliminary Design: November- December 2024
  • Urban Forestry Root Assessment: January - February 2025
  • Design: March- November 2025
  • Construction: December 2025- May 2026

Public Involvement

2025

  • May: Mailed project postcards to the neighborhood and the Brentwood-Darlington Neighborhood Association

2024

  • June: Mailed project notification letters to residents and property owners who live on SE Cooper St.

Project Funding

This project has an overall budget of $568,000.

  • $375,000 PPS Bond
  • $110,000 Fixing Our Streets
  • $83,000 Bureau of Environmental Services

Map

Contact

PBOT Customer Service (by PDX 311)

311Information and customer service
503-823-4000Every day, 7 a.m. to 6 p.m. (excluding federal holidays) Interpretation available | Interpretación disponible | Phiên dịch có sẵn | 提供口译服务 | Доступна интерпретация | Tafsiir la heli karo | Доступний переклад
711Oregon Relay Service

Follow on social media

Neighborhood

Back to top