Construction updates
Overview: March 30 – April 10
In the next two weeks, contractors with PBOT will have several active work zones along NE/SE 82nd Avenue. One lane in each direction on 82nd Avenue will remain open during construction. People traveling on NE/SE 82nd Avenue can expect delays, especially during the morning and evening commutes. Please travel safely around work zones and pay attention to all flaggers, detour signs, and traffic control devices.
Details and traffic impacts:
- NE Fremont to Tillamook – Activating new signals at NE Fremont and NE Tillamook streets will require the existing signals to be shut down and intersection traffic flagged intermittently.
- SE Woodward – Concrete restoration will require lane closures on 82nd and lane closures in the driveway access to Fubonn Shopping Center. No turn restrictions will be in place and flaggers will maintain traffic in all directions. Additional access to Fubonn Shopping Center is available via SE 85th Avenue.
- SE Tibbetts to Brooklyn – Sidewalk work and signal installation will require lane closures on 82nd Avenue.
- SE Lafayette– Activating the new signal will require the existing signal to be shut down and intersection traffic flagged intermittently.
- SE Liebe – Corner ramp construction will require a lane closure on 82nd Avenue and a side street closure of SE Liebe Street.
- SE Raymond Street – Corner ramp and underground work will require lane closures on 82nd Avenue and SE Raymond Street west of 82nd Avenue to beclosed to vehicle traffic just west of 82nd Avenue. This road closure will be in effect Monday–Friday, 24 hours a day. Pedestrians and bicyclists will be able to cross 82nd Avenue at the existing crosswalk. Vehicles can use SE Mitchell Street as an alternate route.
- SE Raymond Court to Insley– Sidewalk and underground utility work will require lane closures on 82nd Avenue.
- SE Insley to Foster– Sidewalk and corner ramp work will require lane closures on 82nd Avenue.
- SE Ramona – Center median island construction will require lane closures on SE 82nd Avenue.
- SE Tolman – Center median island construction will require lane closures on SE 82nd Avenue.
In addition to the above, contractors will be completing punch list items throughout the work zone. Remaining punch list items will require intermittent lane closures on 82nd Avenue.
Visit our project news for past construction updates.
Preliminary design for the second phase of 82nd Avenue safety and transit improvements is available online
A second phase of safety and transit improvements to 82nd Avenue is expected to begin in 2027. Improvements will include completing repaving of the roadway, additional medians to address safety issues, more sidewalk improvements, additional street trees, and transit improvements.
Share your feedback on the draft design concept by emailing: communityaffairs@trimet.org or calling: 503-962-2150
Upcoming events
Wednesday, April 22 | 6–7:30 p.m. | 82nd Avenue Transit Project Community Advisory Committee Meeting | PCC SE Community Hall Annex (2305 SE 82nd Ave., Portland)
Saturday, April 25 | 82nd Avenue Parade of Roses | Begins at: Eastport Plaza (4040 SE 82nd Ave, Portland, OR)
Related efforts
82nd Avenue Transit Project
The 82nd Avenue Transit Project will bring high-capacity FX–Frequent Express bus service along SE 82nd Avenue, between Clackamas Town Center and the Cully neighborhood.
Learn more about the 82nd Avenue Transit Project
82nd Avenue Community Coalition
Throughout the public engagement process, PBOT will be working alongside the 82nd Avenue Coalition. Convened by Oregon Walks, Verde, APANO, and Unite Oregon, this coalition is made up of people and organizations that live, work, and play along 82nd Avenue.