Concrete finishers smooth out concrete on a new driveway connection and segment of sidewalk on NE 82nd Avenue and Siskiyou Street.
Construction updates
Overview: September 15-26
In the next two weeks, contractors with PBOT will have several active work zones along NE/SE 82nd Avenue. One lane in each direction on 82nd Avenue will remain open during construction. People traveling on NE/SE 82nd Avenue can expect delays, especially during the morning and evening commutes. Please travel safely around work zones and pay attention to all flaggers, detour signs, and traffic control devices.
Details and traffic impacts:
- NE Fremont - Signal equipment installation will require the signal to be shut down and the intersection flagged.
- NE Siskiyou – Underground electrical work will require lane closures.
- NE Hancock – Underground storm and corner ramp work will require lane closures.
- NE Russell to Thompson – Paving completed this week. Permanent striping installation will require lane closures. This work will largely be completed at night in order to minimize impacts. Median island construction will begin at Thompson, working north. Work will require daytime lane closures and turn restrictions.
- NE Eugene – Corner ramp work will require lane closures.
- SE Washington – Sidewalk construction on the south side of the street from 80th to 82nd avenues will require a lane closure of the bus and bike lane.
- SE Woodward – Civil and underground work will continue to require lane closures, turn restrictions, and traffic delays near SE Woodward. For convenience, drivers traveling to/from Fubonn Shopping Center are encouraged to use the alternative entrance on 85th Avenue. This entrance can be accessed via SE Brooklyn Street. Additional details below.
- SE 85th Avenue – Sidewalk work on 85th Avenue will begin north of Powell and will continue north, requiring parking restrictions and lane closures. 85th Avenue from Powell to Clinton streets is closed to traffic with the exception of local access.
- SE Brooklyn to Powell – Corner ramp work and underground storm work will require lane closures.
- SE Ramona – Civil and underground work will require lane closures.
Visit our project news for past construction updates.
Heads up! A smoother street is coming to SE 82nd Avenue from SE Clinton to Brooklyn streets
Paving on SE 82nd Avenue mid-September through early October
Travelers and residents are encouraged to use alternate routes, take transit, walk or roll, and avoid driving through the area if possible
The Portland Bureau of Transportation's (PBOT) safety and maintenance upgrade of 82nd Avenue continues, with extensive repairs on SE 82nd Avenue between SE Clinton and Brooklyn streets. These repairs will provide new, smooth pavement and replace failing sections of roadway. The work is expected to have significant traffic impacts. This phase of work is scheduled to begin on Monday, September 22 and is expected to be completed Saturday, October 4. This work is weather dependent, and the schedule may shift.
Raimore Construction will work from 7 a.m. to 4 p.m. Monday through Friday, with one nighttime shift 10 p.m. on Friday, October 3 to 7 a.m. Saturday, October 4.
During this period of construction, one lane of traffic on SE 82nd Avenue will be open in each direction.
82nd Avenue is Open for Business During Construction!
82nd Avenue is home to hundreds of locally-owned and culturally diverse businesses. We invite you to show 82nd Avenue businesses some love during and after construction.
Fubonn Shopping Center is an International Marketplace anchored by a supermarket with products from over 60 countries. The center is also home to four dine in restaurants, a Filipino bakery, bubble Tea as well as a Starbucks. The rest of the mall is filled with locally owned retail businesses and services catering to the everyday needs of the community.
In the coming weeks, construction will be active at SE 82nd and Woodward, adjacent to Fubonn Shopping Center. For convenience, consider using the alternative business access driveway via 85th Avenue to get to Fubonn Shopping Center.
Events
Wednesday, September 17, 12:30 – 5:30 p.m. | Sold-out event! 82nd Ave in Motion: A Tour of Community-led Climate Investments | APANO, 8188 SE Division St, Portland, OR 97206.
Wednesday, September 24, 6 – 7:30 p.m. | 82nd Avenue Transit Project Community Advisory Committee (In-person only) | PCC SE Community Hall Annex (2305 SE 82nd Ave., Portland, OR 97216).
Available grants
Mini-Grants for non-profit organizations available
With Portland Clean Energy Community Benefits Fund (PCEF) mini grants, organizations can apply for up to $5,000 for activities that align with goals of addressing climate change and advancing racial and social justice.
Related efforts
82nd Avenue Transit Project
The 82nd Avenue Transit Project will bring high-capacity FX–Frequent Express bus service along SE 82nd Avenue, between Clackamas Town Center and the Cully neighborhood.
Learn more about the 82nd Avenue Transit Project
82nd Avenue Community Coalition
Throughout the public engagement process, PBOT will be working alongside the 82nd Avenue Coalition. Convened by Oregon Walks, Verde, APANO, and Unite Oregon, this coalition is made up of people and organizations that live, work, and play along 82nd Avenue.