Construction updates
This week PBOT flipped the switch on the signalized pedestrian crossing at NE 82nd Avenue at NE Klickitat Street! This signal gives pedestrians a safer place to cross one of Portland’s most dangerous streets. This crossing improvement was funded by the American Rescue Plan act as a part of PBOT's 82nd Avenue Crossings Project.
Overview: August 4 - 15
In the next two weeks, contractors with PBOT will have several active work zones along NE/SE 82nd Avenue with lane closures and night work. One lane in each direction on 82nd Avenue will remain open during construction. People traveling on NE/SE 82nd Avenue can expect delays, especially during the morning and evening commutes. Please travel safely around work zones and pay attention to all flaggers, detour signs, and traffic control devices. Pedestrian routing will be in place around work zones.
Details and traffic impacts:
- NE Beech to Fremont – Possible landscaping work within the concrete median island will require lane closures.
- NE Siskiyou to Russell – Possible concrete island construction will require lane closures.
- NE Russell to Schuyler – ADA ramp construction, underground storm work, and existing concrete island demolition at Russell will require lane closures.
- SE Harrison to Division – Paving of SE 82nd Avenue between SE Harrison and Clinton is underway. One lane in each direction on SE 82nd Avenue will remain open during paving.
- SE Division (see more details below) - Intersection paving requires left turn restrictions for drivers traveling north and south on SE 82nd Avenue. Significant travel delays are anticipated Monday – Thursdays. Nighttime work will take place from 8 p.m. to 5 a.m. on two Fridays, August 8 and 15.
- SE Clinton to Brooklyn – Underground work and ADA corner ramp construction will require lane closures.
- SE Brooklyn to Powell – Underground work and ADA corner ramp construction will require lane closures.
- SE Kelly – ADA corner ramp work, driveway work at Winco will require lane closures.
Visit our project news for past construction updates.
Heads up! A smoother intersection is coming to SE 82nd Avenue at Division Street with work August 4 through 16
Travelers and residents are encouraged to use alternate routes, take transit, walk or roll, and avoid driving through the area if possible
The Portland Bureau of Transportation's (PBOT) safety and maintenance upgrade of 82nd Avenue continues, with extensive repairs at the intersection of SE 82nd Avenue and Division Street beginning next week. These repairs will provide new, smooth pavement and replace failing sections of roadway. The work is expected to have significant traffic impacts.
This phase of work starts on Monday, August 4 and is expected to complete on Saturday, August 16.
Raimore Construction will work from 7 a.m. to 5 p.m. Monday through Thursday. On two Fridays, August 8 and August 15, contractors will complete their work at night, starting at 8 p.m. and finishing at 5 a.m. the following day.
During this period of construction, one lane of traffic on SE 82nd Avenue will be open in each direction. The traffic signal at SE 82nd Avenue and Division will be turned off and flaggers will direct traffic through the intersection. Drivers traveling north and south on 82nd Avenue will be able to travel straight or turn right at the intersection. Left turns from SE 82nd Avenue to Division Street will not be permitted during working hours.
82nd Avenue is Open for Business During Construction!
82nd Avenue is home to hundreds of locally owned and culturally diverse businesses. We invite you to show 82nd Avenue businesses some love during and after construction.
Events
Saturday, August 16 | 3 - 10 p.m. | Jade International Night Market at PCC SE Campus (2305 SE 82nd Ave). PBOT will table and share information about current construction.
Available grants
Mini-Grants for non-profit organizations available
With Portland Clean Energy Community Benefits Fund (PCEF) mini grants, organizations can apply for up to $5,000 for activities that align with goals of addressing climate change and advancing racial and social justice.
Related efforts
82nd Avenue Transit Project
The 82nd Avenue Transit Project will bring high-capacity FX–Frequent Express bus service along SE 82nd Avenue, between Clackamas Town Center and the Cully neighborhood.
Learn more about the 82nd Avenue Transit Project
82nd Avenue Community Coalition
Throughout the public engagement process, PBOT will be working alongside the 82nd Avenue Coalition. Convened by Oregon Walks, Verde, APANO, and Unite Oregon, this coalition is made up of people and organizations that live, work, and play along 82nd Avenue.