What's happening now?
May 17, 2024 Update
Projects in design:
Major Maintenance Project Advances to Draft Final Design
The project team reviewed comments from the 60 percent public comment period and has incorporated feedback where feasible. The project is now at draft final design. At this stage of the design process, the project team refines final designs and the right-of-way process begins.
In a few key areas, the project team will take a little more time to design improvements. We’ll conduct additional public engagement to make sure designs are aligned with future transit investments and meet the needs of the community.
Areas of 82nd that will be the focus of this additional engagement include:
- Adjacent to Eastport Plaza
- Adjacent to Multnomah Cemetery
- SE Mitchell Street intersection
- Between SE Powell and Holgate boulevards
PBOT is working with Metro, TriMet and partners from Clackamas County to conduct a transit alternatives analysis for potential bus rapid transit service. Between SE Powell and Holgate, the future transit project may include more significant changes to the roadway in this area to address transit delay.
Paving, signals, and ADA ramp work in these areas will be delivered on a different construction timeline and are funded and programmed for construction within the next six years. While we are slowing down on design of these segments to allow for community conversations, we will continue to move forward on the rest of the improvements planned with the Major Maintenance Project.
Construction expected to start this summer and continue through 2026.
May 4, 2024 Update
Projects in construction:
Planned construction activities this month include underground electrical work, ADA corner ramps, and pavement repair on NE/SE 82nd Avenue at the intersections of:
Projects in design:
- The project team has reviewed comments from the public comment period for 82nd Avenue Major Maintenance project 60 percent design concept. We plan to share a design update in the coming weeks.
- The project team will share a 30 percent design concept update this month, after reviewing comments received last fall on the 82nd Avenue Glisan and Davis Signal Improvements project.
- The project team is also working toward final designs on a second package of crossing improvements, at SE Ramona, Tolman, and Lambert streets.
Sign up for Email Updates
Click here to sign up for email updates
Overview
82nd Avenue is in disrepair and needs urgent maintenance and safety repairs. PBOT will invest federal American Rescue Plan Act (ARPA) funding to deliver more lighting, safer crossings, smoother pavement, sidewalk and accessibility improvements, and upgraded traffic signals.
Learn more about the types of improvements below or by viewing the 82nd Avenue Critical Fixes Factsheet.
Improvement Types | |
---|---|
STREET LIGHTING New street lighting will be added and existing street lights will be improved to improve visibility. Click here to learn more. | |
CROSSINGS New signalized pedestrian crossings will be added and safety improvements will be made to existing crossings. Click here to learn more about projects delivering crossings. | |
CORRIDOR SAFETY Updated signage, roadway striping, new signal heads, and technological enhancements will improve safety corridor-wide. Click here to learn more. | |
PAVEMENT & CURB RAMPS A 2-mile segment of 82nd Avenue will be repaved in 2025 and 2026. Additional improvements along these repaved segments include improved curb ramps, crossing and signal improvements, transit improvements, median islands in some locations, and tree planting. Click here to learn more about the Major Maintenance Project. | |
TRAFFIC SIGNALS New and upgraded traffic signals on 82nd Avenue will include modern safety and traffic operation technology.Click here to learn more about projects delivering traffic signals. |
Timeline
Critical Fixes will take place through the end of 2026. Construction of these improvements must be built by the end 2026 or PBOT will lose this federal funding.
Community calls for Critical Fixes
The jurisdictional transfer of 82nd Avenue and Critical Fixes investments are the culmination of years of work by community and their state and local representatives. Community advocates have put lots of resources into developing a vision for 82nd Avenue and have worked hard to hold local governments accountable for addressing the urgent repair and safety needs along the corridor. Watch this video to hear directly from local community about the need for Building a Better 82nd.
Crossings and Traffic Signals
Pedestrian Crossings
Between 2023 and 2026, PBOT and ODOT will add 14 new or upgraded pedestrian crossings on 82nd Avenue to improve safety and fill many of the existing crossing gaps.
Crossings planned for construction in 2023 and 2024 at:
- NE Beech Street
- NE Klickitat Street
- NE Schuyler Street
- SE Ash Street
- SE Clinton Street
- SE Tibbetts Street
- SE Cooper Street*
- SE Knapp Street
- SE Clatsop Street*
Crossings planned for construction in 2025 and 2026 at:
Completed crossings:
* This project will be completed by the Oregon Department of Transportation (ODOT).
Traffic Signals
Between 2023 and 2026, PBOT will construct 7 new or improved traffic signals. Signals will include modern safety and traffic operation technology at the following locations: