Section 1: 122nd Avenue Project Background

Label: Information
Since 2018, the Portland Bureau of Transportation has worked with local residents, businesses, and community organizations to develop a Plan to improve safety on 122nd Avenue.

Project Purpose

The purpose of the Safe Streets and Roads project on 122nd Avenue is to improve safety on 6 miles of 122nd Avenue. This includes intersection redesigns, new street lighting, enhanced bus stops, new pedestrian crossings, enhanced/protected bike lanes, and street trees. The goal is to improve safety for all road users based on recommendations from the 122nd Avenue Plan completed in 2023.

Project Goals

  • Reduce serious crashes.
  • Improve biking and walking conditions.
  • Improve pedestrian access to community amenities such as schools, parks and shopping centers.
  • Increase rates of walking and bicycling in the area.

Project Background

122nd Avenue, 6.4 miles in length, acts as both a north-south regional connector and as the backbone for many neighborhood centers in east Portland. The street carries a lot of travelers with large vehicles volumes, a bus line, and many people walking, biking, and rolling. This is a hardworking street serving essential jobs and services. 

122nd Avenue from Sandy to Foster is a street with a high frequency of crashes, including high-severity crashes. As a result, the city prioritizes investments in transportation safety improvements in this area.

  • Between 2016 and 2025, 22 people died on 122nd Avenue in traffic crashes.
  • Twelve of them were people walking.
  • More than two people are killed per year on average.
  • Crashes with people walking occur all along 122nd Avenue but are concentrated near NE Glisan St and SE Powell Blvd.
  • There are five high crash intersections along the corridor
The existing cross section of 122nd Avenue prioritizes vehicles over all other modes.

Project Timeline

2025 to Early 2026

  • Analyzing traffic data
  • Modeling preliminary design alternatives
  • Hearing from the community about their experiences which will help us inform our designs

Mid 2026 to 2027

  • Continue to refine design alternatives with technical input from the team and present feasible options to the community

Late 2027

  • Construction begins
  • Keep the community informed with regular updates about schedule, progress, and expected impacts