UPDATED: What is happening now?
- Traffic chicane pilot project on SE 62nd is complete.
- Speed cushions on SE Harold, 122nd to 136th are complete.
- Speed cushions on NE Prescott, 64th to 70th are complete.
- Speed cushions on NE Prescott, 105th to 121st Pl is complete.
- Traffic chicane pilot projects on NE 119th Avenue is complete.
- NE Rose Parkway (NE Fremont to NE 141st) project is complete.
- Projects awaiting construction include:
- NE Knott, NE 21st to NE 33rd
- NE Multnomah, 16th to 21st
- SW 45th at SW Carson, Brugger, and Marigold Trail and Gabriel Park Crossings.
Updated 9/24/2026
Project Locations (2025-2029)
| Street | Start Point | End Point | Expected Construction Year |
|---|---|---|---|
| NE Rose Parkway | NE Fremont | NE 141st Dr | 2026 (Complete) |
| NE Prescott | NE 105th | NE 121st Pl | 2026 (Complete) |
| SE Harold Street | SE 122nd | SE 136th | 2026 (Complete) |
| NE Knott | NE 21st | NE 33rd | 2026 (Awaiting construction) |
| SE Steele | SE 28th | SE 41st | 2026 or early 2027 (In design) |
| SE 174th | SE Haig | SE Marie | 2025 (Complete) |
| NE Prescott | NE 64th | NE 70th | 2026 (Complete) |
| SE 103rd | SE Harold | SE Foster | 2027 (In design) |
| SE 17th | SE McLoughlin | SE Bybee | 2027 (In design) |
| SW 39th Drive | SW Beaverton-Hillsdale Hwy | SW Hamilton | 2027 (In design) |
| SE Market | SE 104th | SE 117th | 2027 (In design) |
| SE Duke | SE 56th | SE 72nd | 2027 (in design) |
Project Locations (2021-2025)
| Street | Start Point | End Point | Expected Construction Year |
|---|---|---|---|
| NE Sacramento | NE 111th | NE 122nd | 2021 (Completed) |
| NE Shaver | NE 122nd | NE 141st | 2021 (Completed) |
| SE 60th | SE Flavel St. | SE Flavel Dr. | 2021 (Completed) |
| SE Nehalem | SE 67th | SE 72nd | 2021 (Completed) |
| SE 64th | SE Clatsop | SE Flavel Dr. | 2021 (Completed) |
| SE Flavel | SE 52nd | SE Clatsop | 2022 (Completed) |
| N Columbia Way | N Fessenden | N Smith | 2022 (Completed) |
| N Oswego | N Lombard | N Columbia | 2022 (Completed) |
| N Buchanan | N Lombard | N Columbia | 2022 (Completed) |
| NE Ainsworth | NE MLK Jr. | NE 15th | 2023 (Completed) |
| N Portsmouth | N Lombard | N Fessenden | 2023 (Completed) |
| NE Fremont | NE 122nd | NE 141st | 2023 (Completed) |
| SE 135th | SE Stark | SE Division | 2023 (Completed) |
| NE 139th | NE Glisan | SE Stark | 2024 (Completed) |
| SW 45th | SW Multnomah | SW Taylors Ferry | 2026 (Awaiting Contractor). Approval for speed limit reduction by ODOT was rejected in 2024. Installing speed cushions at SW Carson, Marigold Trail Crossing, SW Gabriel Park Trail Crossing and SW Brugger/48th. |
| SW Broadway Dr. | SW Patton | SW Broadway Ave | 2025 (Completed) |
| SE Harold | SE 92nd | SE 122nd | 2024 (Completed) |
| NE San Rafael | NE 125th | NE 138th | 2025 (Completed) |
| Chicane Pilot Projects | |||
| SW Burlingame Ave - Chicane Pilot | SW Chestnut | SW Capitol Hwy | 2023 (Completed) |
| SE 62nd Ave - Chicane Pilot | SE Clatsop | SE Flavel | 2026 (Completed) |
| NE 119th - Chicane Pilot | NE San Rafael | NE Halsey | 2026 (Completed) |
Map of Projects (2021-2025)
View map of 2021 to 2025 projects
This is a map showing projects to reduce speed on neighborhood cut-through routes. It shows the locations for speed bumps, speed cushions and other traffic calming projects on streets throughout the city. PBOT understands that this map is not accessible for users of assistive technology. Due to the complexity of the information the map provides and the currently available map platforms at the city, it will take some time to make adjustments. We thank you for your patience while we work on a technology-based solution. As we work toward providing accessibility, please contact email address and/or program name phone number to reach PBOT staff who can assist you to get the data you need from the map. You can also contact PBOT’s ADA Coordinator at Lisa.Strader@portlandoregon.gov or at 503-823-5703.
Again, thank you for your understanding and patience.
How were the projects chosen?
PBOT developed an evaluation matrix combining traffic operations like automobile speeds and volumes, policy considerations like priority safe routes to school corridors, and neighborhood impacts using PBOT's Equity Matrix. Streets with the highest speeds and traffic volumes in areas of highest needs were prioritized.
Funding is from the local 10-cent gas tax within the Fixing Our Streets program.
Program highlights
NE 119th Avenue Traffic Chicane project
Traffic chicanes were installed NE 119th Ave in spring of 2026. Traffic chicanes help slow vehicles by requiring people driving to navigate the street more cautiously. PBOT has received speeding complaints from residents on NE 119th and the traffic chicanes are expected to reduce speeds.
The traffic chicanes are installed using more temporary materials. The pilot project's goal is to determine if chicanes can reduce speeds more cost-effectively on narrow streets compared to speed bumps. Other streets in the pilot are SE 62nd and SW Burlingame avenues.
Traffic speed data is collected both before and after implementation to determine impacts to the street. SW Burlingame Ave is the first location in the pilot project.
Why traffic calming on NE 119th Avenue?
NE 119th Avenue is near Sacramento Elementary school. Nearby streets have traffic calming speed bumps. This project aims to lower speeds similarly to other streets and cost less than a typical speed bump project.
SE 62nd Traffic Chicane project
Traffic chicanes are coming to SE 62nd Ave in spring or summer 2026. Traffic chicanes help slow vehicles by requiring people driving to navigate the street more cautiously. PBOT has received speeding complaints from residents on SE 62nd Ave and the traffic chicanes are expected to reduce speeds. The traffic chicanes will be installed on SE 62nd Ave from SE Clatsop to SE Flavel streets.
The traffic chicanes are installed using more temporary materials. The pilot project's goal is to determine if chicanes can reduce speeds more cost-effectively on narrow streets compared to speed bumps. Other streets in the pilot are NE 119th and SW Burlingame avenues. Here is a picture of the traffic chicanes on SW Burlingame.
Traffic speed data is collected both before and after implementation to determine impacts to the street.
Public involvement opportunities
Letter to SE 62nd Avenue residents about traffic chicane project:
Letter to NE 119th Avenue residents about traffic chicane project:
View PBOT presentation to the Russell Neighborhood Association on NE San Rafael traffic calming project and NE Sacramento-Knott greenway project:
View presentation to the Woodlawn Neighborhood Association about the NE Ainsworth Street, NE MLK Blvd to NE 15th Ave:
Will my street be considered?
Please contact 311 to report speeding or other safety issues. You can also look at the last 10 years of PBOT's traffic data available on this web map. This will show you similar data that PBOT staff use to evaluate traffic operations.
Funding
Funding comes from the local 10-cent gas tax within the Fixing Our Streets program. From 2024 to 2028, $2 million is set aside for traffic calming projects. Several projects are funded from other Fixing Our Streets funds set aside for safety improvements in neighborhoods.