(Updated 10/6/2026) This schedule is subject to change due to weather, contractor staff availability, and material availability.
Contractor work hours are 7am to 5pm, with intent to avoid night and weekend work.
Contractor work hours are 7am to 5pm, with intent to avoid night and weekend work.
Project Map
Construction Schedule
| Location | Work type | Schedule | Impact |
|---|---|---|---|
| Traffic signal at 57th and NE Halsey | Electrification of traffic signal by utility company | Thursday 10/9/26 9am - 4pm | Flagging at intersection. Expect delays. |
| Traffic signal at 57th and NE Halsey | Traffic signal turn-on | Dependent on the sub-contractor's schedule, but should take place the week of 10/12-10/16. | Flagging at intersection. Expect delays. |
| NE 47th Ave and NE Halsey | Repair of steepness of outside travel lanes. | Work has not been scheduled yet | Vehicles to detour around construction. |
| NE Halsey between 57th Ave - 59th avenues | Base repair road reconstruction and ADA ramp construction | To be determined • The roughest section in the project area is NE Halsey between 57th–59th, and we're working hard to include it as an extension of the current project. • We ran out of time to complete this paving work in the 2026 construction season, and we're still finalizing the funding package. • 57th - 59th requires 17-inch full depth base repair and 12 new ADA curb ramps, making it a much larger effort than a standard 2-inch grind and pave. | Vehicles to detour around paving. |