Lots of activity has been taking place on NE Shaver Street over recent weeks, with crews making progress at several locations simultaneously.
We appreciate the patience and flexibility of nearby residents, especially those along Shaver Street who are experiencing construction noise, activity near their homes, and changing traffic patterns as work continues.
This month, work will begin shifting from stormwater to sidewalk and driveway excavation, beginning on the west end of Shaver Street at NE 102nd Avenue.
Expected three-week schedule
This week: November 2nd - 6th
- NE 109th Avenue, south of Shaver: Install stormwater facilities
- NE 112th Avenue, south of Shaver: Begin stormwater facility installation
- 11000 block and between NE 113th and 115th avenues: NW Natural gas line relocations
- Multiple locations: temporary pavement repair
Next week: November 9th - 13th
- NE 102nd - 105th Avenues: Sidewalk preparation work, excavation
- NE 113th Avenue: Install stormwater pipes on southeast corner
- Between NE 113th and 115th avenues: NW Natural gas line relocations
November 16th - 20th
- NE 102nd - 105th Avenues: Sidewalk work continues
- Between NE 113th and 115th avenues: NW Natural gas line relocations
Work hours are between 7 a.m. and 6 p.m., Monday through Friday. Schedules can change for various reasons, like weather or unforeseen delays.
For more information or project questions:
Abra McNair | Project Manager
abra.mcnair@portlandoregon.gov | 971-501-0419
Construction impacts
What to expect during construction
- Noise, dust, and vibration from equipment
- Temporary street closures or detours, which may mean longer trips around the work zone
- Changes to parking and access to homes and driveways
- Construction vehicles and crews working in your area
- Some Line 22 bus stops will be closed intermittently. Signs should be posted at affected stops, and Service Alerts will be updated on the TriMet website.
People Driving
Road closures and detours are in place during work hours (7 a.m. - 6 p.m., Monday through Friday). Open trenches will be covered with steel plates and roads reopened at the end of each day.
Thank you for driving slowly and cautiously, especially as darker fall conditions reduce visibility.
People Walking
Crews will have a spotter in place to allow pedestrian access around work zones as needed
Upcoming events & opportunities
Portland 2045 Transportation System Plan (TSP) Fall Open House
The Transportation System Plan is the 20-year plan to guide transportation project, programs, policies, and investments in Portland. Help prioritize Portland's next 20 years of transportation projects!
District 1 Open House:
TOMORROW: Wednesday, Nov 4, 5-7 p.m.
Historic Parkrose: 10402 NE Sandy Blvd.
Prefer to participate online?
An online open house and survey will be available October 19 to December 7. This survey gives you an opportunity to share your high-level priorities for Portland's transportation system and, if you'd like, provide more detailed feedback on which projects you think should be prioritized. Please note:If you plan to review the project lists and provide detailed feedback, we recommend using a computer or printing the project lists for the best user experience.
Participate in the online open house and survey
Join the Fixing Our Streets Oversight Committee (apply by November 5th)
The Portland Bureau of Transportation is recruiting committee members to serve a four-year term on the Fixing Our Streets Oversight Committee (FOSOC)! The application deadline is Thursday, November 5, 2026, at 11:59 p.m.
Are you interested in learning about Portland's transportation system? Do you want to help ensure accountability for the Fixing Our Streets program? If so, please consider this unique volunteer opportunity!
The Fixing Our Streets Oversight Committee has a newly expanded role in ensuring the accountability of theFixing Our Streets program which now includes the Transportation Utility Fund and the Street Damage Restoration Fund, in addition to the 10-cent Local Gas Fund and Heavy Vehicle Use Fund.
If you are interested in volunteering on the Fixing Our Streets Oversight Committee, review the committee volunteer (non-paid) position description and complete the application form here.
Other Parkrose area transportation projects
122nd Avenue Projects in Construction
There are many projects along 122nd Avenue that are under construction or will be soon.
NE Fremont Street Sidewalk Infill (118th Avenue to 122nd Avenue)
Currently in design with construction expected by 2028. This project will construct continuous sidewalk on the north side of Fremont Street west from NE 122nd Avenue to 118th Avenue.
Neighborhood Greenway Gateways
Improvements at NE 112th Avenue and Fremont Court are expected to happen before the end of 2026.
NE 106th Avenue Multi-Use Pathway
PBOT recently improved a dirt path connection between NE 106th Avenue and NE San Rafael Street in the Parkrose Heights neighborhood.