Interlaken, Inc., a contractor hired by the Portland Bureau of Transportation (PBOT), is building a sidewalk on the south side of NE Shaver Street between 102nd and 115th avenues to improve access to Parkrose schools. Project work also includes stormwater facilities, updated streetlighting, and new street trees.
Expected construction schedule: Three-week look-ahead
Active work is allowed between 7 a.m. and 6 p.m., Monday through Friday. Some weekend work may take place in spring 2027.
The following activities are planned over the next three weeks on NE Shaver Street:
Week 1: October 14 - 16
- Portland Water Bureau completes water meter relocations and paving repair
- Pavement saw cutting to prep for stormwater installation
- Fence removals from public right-of-way
- Install stormwater sump, sedimentation maintenance hole, and pipes east of NE 102nd Avenue and Shaver Street intersection (Work Area 1 in diagram)
Week 2: October 19 - 23
- Tree and vegetation removal
- Install stormwater sumps, sedimentation maintenance holes, and pipes mid-block and west of NE 105th Avenue (Work Areas 2 & 3)
Week 3: October 26 - 30
- Install stormwater sump, sedimentation maintenance hole, and pipes east of NE 105th Avenue (Work Area 4)
- Temporary paving at all completed stormwater locations
Schedules can change for various reasons, like weather or unforeseen delays.
What to expect during construction
Travel Impacts
People Driving
Road closures will be in place near NE 102nd and 105th avenues during work hours (7 a.m. - 6 p.m., Monday through Friday) while sed and sump installations are in progress.
Open trenches will be covered with steel plates and roads reopened at the end of each day.
If possible, we recommend using other routes during work hours. Local access for residents will be maintained throughout construction.
Drive slowly, watch for students and people walking. Many Parkrose students and families use NE Shaver Street to access school. Thank you for driving cautiously, especially as darker fall conditions reduce visibility.
People Walking
Crews will have a spotter in place to allow pedestrian access around work zones as needed.
TriMet Buses
Some Line 22 bus stops will be closed intermittently based on work nearby. Signs should be posted at affected stops, and Service Alerts will be updated on the TriMet website.
Noise & Environmental Impacts
The contractor will be using large machines to excavate trenches and pits for the sed and sump installations. Expect noise, vibration, and dust.
About sumps and sedimentation maintenance holes
A sump maintenance hole (sump) is a large, concrete cylinder installed under a street that is connected to a storm drain and a separate tank, called a sedimentation maintenance hole (sed).
Storm drains direct stormwater first into a sed that separates out debris and pollutants and then to the sump, where water filters out of the many holes to slowly soak into the surrounding soil, replenishing groundwater supplies.
Sumps are big! They are usually four feet in diameter, and several holes along the sides are the size of a softball. They generally descend 30 feet below the street.
These facilities help manage stormwater, protect surface waters (like lakes, rivers, and streams), replenish groundwater and surface water supplies, and prevent sewer overflows and basement backups.
For more information:
Abra McNair | Project Manager
abra.mcnair@portlandoregon.gov | 971-501-0419
Other Parkrose area transportation projects
122nd Avenue Projects in Construction
There are many projects along 122nd Avenue that are under construction or will be soon.
NE Fremont Street Sidewalk Infill (118th Avenue to 122nd Avenue)
Currently in design with construction expected by 2028. This project will construct continuous sidewalk on the north side of Fremont Street west from NE 122nd Avenue to 118th Avenue.
NE 106th Avenue Multi-Use Pathway
PBOT is improving a dirt path connection between NE 106th Avenue and NE San Rafael Street in Parkrose Heights. Construction is expected to be complete this October.
Neighborhood Greenway Gateways
Improvements at NE 112th Avenue and Fremont Court are expected to happen before the end of 2026.