Springwater Connector Neighborhood Greenway 6/18/20 Construction Update

News Article
Map of Springwater Connector Neighborhood Greenway
The Portland Bureau of Transportation (PBOT)'s construction contractor will begin work at the SE Springwater/87th location the week of July 13. This update provides the planned construction schedule of this project.
Published
Updated

PBOT's construction contractor, Interlaken, Inc. will begin work at the Springwater/87th location the week of July 13. Work in this area will start with installation of erosion control and tree cutting.

Work throughout the remainder of July will be focused on grading and installing a culvert at the path connection.

Work in August will move onto SE 87th Ave including installation of stormwater manholes, construction of the sidewalk, and grading and paving of the street.

The Springwater/87th location will be mostly complete by the end of August, except for street lighting and signing and striping.

Work will then move to the SE Flavel/78th pedestrian crossing.

Construction of street improvements on SE 75th Place is scheduled for September and work in Flavel Park is scheduled for October.

The project is scheduled to be complete in January 2021.