This local improvement district (LID) includes street improvements to SE 82nd Ave and SE Bybee Blvd.
–
On this Page
Project Components
Streets included:
SE 82nd Avenue from Bybee Boulevard to 168 feet south of Cooper Street
SE Bybee Boulevard from 82nd Avenue to 37 feet east of 81st Place
Project Timeline
LID formed by City Council on April 6, 2011.
Design completed on July 3, 2012.
Contract awarded on September 18, 2012.
Construction substantially completed on August 16, 2013.
Construction final completion on October 1, 2013.
Final assessment approved by City Council on April 2, 2014.
Trees planted were Black Tupelo and Hornbeam.
Project Funding
Property owners funded this local improvement district with partial project funding by the Portland Water Bureau of water system work.