Project Components
Streets included:
- SE 152nd Avenue from Barbara Welch Road to south of Henderson Way (full street improvements)
- SE 152nd Avenue from south of Henderson Way to north of Bybee Drive (partial street improvements - west side only)
Project Timeline
Advertised for bids on March 24, 2008
Contract awarded to Parker Northwest Paving on May 21, 2008
City Engineer issued Notice to Proceed to contractor on June 20, 2008
Paving completed on November 26, 2008
Traffic signal at SE Foster and Barbara Welch Roads (a prerequisite to opening SE 152nd Avenue) activated on December 3, 2008
Swale vegetation planting completed on December 3, 2008
Stop signs at the newly-realigned intersection of SE 152nd Avenue, SE Barbara Welch Road and SE Barbara Welch Lane completed on December 4, 2008
Speed bump installation completed on December 5, 2008
SE 152nd Avenue opened on December 5, 2008
Tree planting in swales completed on February 18, 2009
Final assessment completed on April 1, 2009
Transformer relocation and sidewalk infill construction on west side of SE 152nd Avenue between Henderson Way and Knapp Drive completed on April 24, 2009
Tree planting in planting strips completed on April 28, 2009
The height of the previously-installed speed bumps was increased by the contractor on June 4, 2009.
Project Funding
Property owners are funding this local improvement district with additional funding from the Waterleaf development and from the Bureau of Environmental Services.