This local improvement district (LID) includes street improvements to NE Winchell Street.
–
On this Page
Project Components
Streets included:
- NE Winchell Street east of Mallory Avenue
Project Timeline
Advertised for bids on March 24, 2008
Contract awarded to Parker Northwest Paving on May 21, 2008
City Engineer issued Notice to Proceed to contractor on June 20, 2008
Paving completed on August 4, 2008
Swale vegetation completed on November 12, 2008
Final assessment completed on December 10, 2008
Street tree planting planned for the week of December 22, 2008
Project Funding
Property owners funded this local improvement district.