This local improvement district (LID) includes street improvements to NE 92nd Drive.
–
On this Page
Project Components
Streets included:
- NE 92nd Drive from the Columbia Slough to Alderwood Road
Project Timeline
Advertised for bids on June 15, 2009.
Contract awarded to Tri-State Construction Inc. on August 12, 2009.
Notice to Proceed for construction issued on September 10, 2009.
NE 92nd Drive was reopened to traffic on June 18, 2010 following fabrication and installation of the new pedestrian and bicycle bridge; no further closures planned.
Final assessment completed on 10/27/10.
Project Funding
Property owners funded this local improvement district.