Project Components
Streets included:
- Intersection of NE 87th Avenue and Columbia Blvd.
Project Timeline
Construction of northeast and northwest corners of intersection completed Summer 2007.
Advertised for bids on June 15, 2009.
Contract awarded to Tri-State Construction Inc. on August 12, 2009.
Notice to Proceed for construction of south side of intersection and sanitary sewer work issued on September 10, 2009.
Intersection was closed on January 4, 2010 and reopened February 24, 2010.
Sanitary sewer extension completed January 29, 2010.
Stormwater sewer installation completed January 29, 2010.
Utility relocation by Northwest Natural completed on February 9, 2010. Utility relocation by Portland Water Bureau completed on February 11, 2010.
Paving completed on February 19, 2010.
Final assessment completed on 10/27/10.
Project Funding
Property owners are funding this local improvement district. The Bureau of Environmental Services is funding extension of the sanitary sewer.