Streets included:
- East side of NE 52nd Avenue from 85 feet north of NE Wygant Street to the south right-of-way line of NE Alberta Street
South side of NE Alberta Street from the east right-of-way line of NE 52nd Avenue to 265 feet west of NE 55th Avenue
Project Timeline
LID formed by City Council on April 3, 2013
Design completed on April 29, 2014.
Advertised for bids on May 19, 2014.
Opened bids on June 12, 2014.
Executed contract with Kodiak Pacific Construction, Inc. on July 31, 2014.
Issued Notice to Proceed to Kodiak Pacific Construction, Inc. on August 25, 2014.
Paving completed on September 22, 2014 with speed bumps installed on September 25, 2014.
Final assessment approved by City Council on December 30, 2015.