NE 52nd Ave and Alberta Street LID

Transportation
Completed
This local improvement district (LID) includes street improvements to NE 52nd and NE Alberta Streets.
On this Page

Project Components

Streets included:

  • East side of NE 52nd Avenue from 85 feet north of NE Wygant Street to the south right-of-way line of NE Alberta Street
  • South side of NE Alberta Street from the east right-of-way line of NE 52nd Avenue to 265 feet west of NE 55th Avenue

Project Timeline

LID formed by City Council on April 3, 2013

Design completed on April 29, 2014.

Advertised for bids on May 19, 2014.

Opened bids on June 12, 2014.

Executed contract with Kodiak Pacific Construction, Inc. on July 31, 2014.

Issued Notice to Proceed to Kodiak Pacific Construction, Inc. on August 25, 2014.

Paving completed on September 22, 2014 with speed bumps installed on September 25, 2014.

Final assessment approved by City Council on December 30, 2015.

Project Funding

Property owners are funding this project.