The Portland Bureau of Transportation (PBOT) is constructing Local Improvement District street improvements on NE 27th and Holland Street.
Construction expected to finish in late 2020
What's happening now?
This project is currently under construction.
Project Timeline
LID formed by City Council on July 12, 2017
Notice to Proceed issued to the contractor on September 13, 2019 with substantial completion anticipated in November 2020.
Project Components
Streets include:
- NE 27th Avenue from NE Columbia Blvd. to NE Holland Street
- NE Holland Street from NE 27th Avenue to 25 or 52 feet east of NE 27th Avenue
Project Funding
Property owners are providing funding for this project with overhead costs funded by the Portland Bureau of Transportation.