NE 136th Avenue Phase I LID

Transportation
Completed
This local improvement district (LID) includes street improvements to NE 136th Avenue.
On this Page

Project Components

Streets included:

  • NE 136th Avenue north of Prescott Court (from north property line of 4525 NE 136th Avenue) to 80 feet south of Whitaker Way

Project Timeline

LID formed by City Council on September 1, 2010.

Design completed on June 11, 2012.

Advertised for bids on June 20, 2012.

Bids opened on July 12, 2012.

Contract awarded to Kodiak Pacific Construction on September 12, 2012.

Paving completed on November 7, 2012.

Tree planting completed on March 25, 2013; species planted were Spring Flurry Serviceberry and Mountain Silverbell.

Swale vegetation planting completed on April 10, 2013.

Final assessment pending on May 7, 2014; no additional project updates planned.

Project Funding

Property owners are funding this local improvement district with partial funding from the Portland Bureau of Transportation for overhead costs.