N Suttle Road Local Improvement District

Transportation
Engineering And Design
The Portland Bureau of Transportation (PBOT) and the Bureau of Environmental Services (BES) are constructing street, sidewalk, stormwater and sanitary sewer improvements on N Suttle Road.
Poor pavement condition and lack of stormwater facilities on N Suttle Road
Spring 2023
On this Page

Sign Up for Email Updates

Get the latest updates about this project.

What's happening now?

Design for this project is complete. Project bidding was held on December 8, 2022. We will be requesting City Council approval for contract authorization in February, 2023.

Project Timeline

  • Local Improvement District formed by Portland City Council on August 30, 2017
  • Design completed in July 2022
  • Construction expected to start in spring 2023 and finish in 2024

Project Components

  • Fully reconstructed street built with 9.5"-thick concrete to support heavy freight traffic and reduce future maintenance costs
  • 3,210 square feet of stormwater drainage facilities with 26,000 gallons of capacity to reduce flooding and protect the environment
  • New sidewalk (5 to 6 feet wide) on the north side of the street
  • 45 additional street trees

Project Funding

$10 million from property owners with overhead costs funded by the Portland Bureau of Transportation