important alert
State closes I-5 southbound at Rose Quarter for 5 weeks starting Sept. 11

Plan for major delays. More at i5rosequarter.org. Visit Shift Your Trip to keep Portland moving.

informational alert
Portland is a Sanctuary City

SW Fairmount Boulevard Landslide Response

Label: Transportation
Label: Engineering and design
A landslide on SW Fairmount Boulevard occurred in March 2026, resulting in the temporary closure of SW Fairmount Boulevard.
Summer and fall 2026
Location description
SW Fairmount Boulevard at SW Sherwood Place
Debris and vegetation dislodged from the eastern edge of SW Fairmount Boulevard after heavy rains in March.

Route closures in effect - now includes people walking and biking

As of March 13, 2026, marked and signed closures are in effect along portions of SW Fairmount Blvd. A soft closure/local access only is in effect to the north and south of the landslide area. A full closure is in effect at the landslide area, itself. Beginning the week of September 8, 2026, hard closures in the slide area will apply to people walking and biking, as well as to people driving. This change is to ensure the safety of contractor crews and the traveling public during construction.

A detour route directs drivers to use SW Fairmount Boulevard to access area destinations. Segments of SW Fairmount Boulevard are signed as Local Access Only between SW Talbot Road and SW Marquam Hill Road, to the north and south of the landslide closure.

Sign up for email updates

Stay up to date on the latest news and information about the SW Fairmount Boulevard Landslide Response. Emails will be sent when major changes take place, especially related to access, construction activity, or project timelines.

Sign up for email list

Project updates

September 4, 2026

PBOT and its contractor plan to begin construction during the week of September 8th, with completion anticipated in October.

The contractor's initial activities will include mobilizing equipment and materials and installing traffic and erosion control. Next, crews will excavate and haul away debris before constructing the rock buttress, stormwater, and drainage improvements. Crews will then repair and restore the asphalt and shoulder on SW Fairmount Blvd before completing construction.

During construction, hard closures in the slide area will apply to people walking and biking, as well as to people driving. This change is to ensure the safety of contractor crews and the traveling public during construction.

August 31, 2026

Through the end of August, City staff completed bid plans and worked through contracting with the construction contractor. City arborists removed and pruned two hazard trees in the slide area, in preparation for construction. PBOT is targeting September to begin construction and October to complete construction.

August 14, 2026

Through the end of July and the beginning of August, City staff completed 95% plans and final plans. Utilities in the vicinity also began relocating their service lines in preparation for construction. The project team is now focused on construction contracting and site preparation. PBOT is targeting September to begin construction.

July 16, 2026

In the first half of July, City staff completed 30% plans, the first major design milestone for the slope stabilization project. The project team is now progressing towards 95% plans and final plans (August-September) and targeting late summer/early fall to begin construction.

June 25, 2026

In June, PBOT installed speed reader boards to encourage slower speeds in the Council Crest neighborhood. PBOT and BES staff also continued designing the rock buttress that will stabilize the landslide slope, as well as stormwater improvements on the west side of SW Fairmount Blvd.

June 5, 2026

Over the past two weeks, PBOT and BES staff began designing the rock buttress that will stabilize the landslide slope, as well as stormwater improvements on the west side of SW Fairmount Blvd.

PBOT staff also collected additional vehicle speed and volume data and identified locations for speed reader boards to encourage slower driving speeds in the neighborhood. These speed reader boards will be installed in early June.

May 22, 2026

This week, PBOT and BES staff coordinated with affected property owners to identify a preferred alternative for slope stabilization improvements. The project team will begin designing these improvements the week of May 25, 2026.

PBOT staff also shared project updates at the Southwest Hills Residential League (SWHRL) monthly meeting on May 20, 2026.

May 15, 2026

In the first half of May, PBOT and BES staff continued refining and evaluating alternatives for the future slope stabilization improvements. A preferred alternative will be advanced to design shortly.

In parallel, staff developed initial designs for civil and stormwater drainage modifications on Fairmount Blvd and on the west side of Fairmount Blvd, across the street from the landslide.

May 1, 2026

Over the past two weeks, PBOT staff finalized right-of-way resolution in the landslide area and continued coordinating with impacted utility providers on temporary utility relocation needs.

PBOT and BES staff developed several alternatives and cost estimates for the future slope stabilization improvements. Staff are currently evaluating and refining these alternatives before identifying a preferred alternative to advance for further design, engineering, and construction.

April 16, 2026

This week, PBOT staff installed an updated detour route around the slide closure area. The detour directs drivers to use SW Fairmount Blvd to avoid the slide closure area when accessing area destinations.

Staff from the BES Materials Testing Lab continued testing field samples, and PBOT and BES staff continued developing solution alternatives, cost estimates, and a geotechnical report for the project. These deliverables will be produced in the coming weeks and will inform the preferred alternative that's selected for further design, engineering, and construction.

April 10, 2026

This week, PBOT staff worked to finalize right-of-way resolution in the landslide area and coordinated with impacted utility providers on future utility relocation needs. Staff also connected with adjacent property owners to walk the broader corridor and to discuss the landslide's impacts.

PBOT and BES staff are now focused on developing the geotechnical report, solution alternatives, and cost estimates for the project. These deliverables will be produced in the coming weeks and will inform the preferred alternative that's selected for further design, engineering, and construction.

April 3, 2026

This week, PBOT surveyors delivered topographic survey of the landslide area and are finalizing right-of-way resolution. Bureau of Environmental Services (BES) also completed soil borings to collect soil data. These efforts will inform the geotechnical report and solution alternatives that will be developed in the coming weeks.

This week PBOT also finalized an updated detour plan that will be posted in the field and direct drivers to use Fairmount Blvd (West) to detour around the slide area closure. Additionally, in response to reports of barricades and signs at the slide closure being moved, PBOT reinforced both sides of the slide area with concrete blocks and secured metal barricades to prevent unwanted adjustments.

March 25, 2026

PBOT surveyors are completing field survey at the landslide site. Exploratory borings to collect soil data will occur the week of 3/30/26. Signed closures remain in place, and a map of area closures has been added to the project website.

March 19, 2026

Portland Bureau of Transportation (PBOT) surveyors are collecting field survey data at the landslide site. Contractors hired by BES will begin exploratory borings to collect soil data shortly. A signed detour route is in place and will likely be in effect into the summer months. The detour route will be added to the project website shortly.

 

Background

On Thursday, March 12, a landslide following heavy rains forced the closure of SW Fairmount Blvd. PBOT responded by closing the affected section of Fairmount Blvd to traffic and putting a signed detour in place.

Map

Closure area on SW Fairmount Blvd, in response to a landslide.

Contact

PBOT Customer Service (by PDX 311)

311Information and customer service
503-823-4000Every day, 7 a.m. to 6 p.m. (excluding federal holidays) Interpretation available | Interpretación disponible | Phiên dịch có sẵn | 提供口译服务 | Доступна интерпретация | Tafsiir la heli karo | Доступний переклад
711Oregon Relay Service

Follow on social media

Back to top