informational alert
Portland and the federal government

Learn about our sanctuary city status, efforts to block federal overreach: Portland.gov/Federal

SW Fairmount Boulevard Landslide Response

Label: Transportation
Label: Engineering and design
A landslide on SW Fairmount Boulevard occurred in March 2026, resulting in the temporary closure of SW Fairmount Boulevard.
Spring 2026
Location description
SW Fairmount Boulevard at SW Sherwood Place

Route closures in effect

As of March 13, 2026, marked and signed closures are in effect along portions of SW Fairmount Blvd. A soft closure/local access only is in effect to the north and south of the landslide area. A full closure is in effect at the landslide area, itself. Marked and signed closures remain open to people walking and biking.

An updated detour route was put into effect on April 15, 2026.

Travelers must adhere to posted warning signs, detours, and closures.

A detour route directs drivers to use SW Fairmount Boulevard to access area destinations. Segments of SW Fairmount Boulevard are signed as Local Access Only between SW Talbot Road and SW Marquam Hill Road, to the north and south of the landslide closure.

Sign up for email updates

Stay up to date on the latest news and information about the SW Fairmount Boulevard Landslide Response. Emails will be sent when major changes take place, especially related to access, construction activity, or project timelines.

Sign up for email list

Project updates

May 1, 2026

Over the past two weeks, PBOT staff finalized right-of-way resolution in the landslide area and continued coordinating with impacted utility providers on temporary utility relocation needs.

PBOT and BES staff developed several alternatives and cost estimates for the future slope stabilization improvements. Staff are currently evaluating and refining these alternatives before identifying a preferred alternative to advance for further design, engineering, and construction.

April 16, 2026

This week, PBOT staff installed an updated detour route around the slide closure area. The detour directs drivers to use SW Fairmount Blvd to avoid the slide closure area when accessing area destinations.

Staff from the BES Materials Testing Lab continued testing field samples, and PBOT and BES staff continued developing solution alternatives, cost estimates, and a geotechnical report for the project. These deliverables will be produced in the coming weeks and will inform the preferred alternative that's selected for further design, engineering, and construction.

April 10, 2026

This week, PBOT staff worked to finalize right-of-way resolution in the landslide area and coordinated with impacted utility providers on future utility relocation needs. Staff also connected with adjacent property owners to walk the broader corridor and to discuss the landslide's impacts.

PBOT and BES staff are now focused on developing the geotechnical report, solution alternatives, and cost estimates for the project. These deliverables will be produced in the coming weeks and will inform the preferred alternative that's selected for further design, engineering, and construction.

April 3, 2026

This week, PBOT surveyors delivered topographic survey of the landslide area and are finalizing right-of-way resolution. Bureau of Environmental Services (BES) also completed soil borings to collect soil data. These efforts will inform the geotechnical report and solution alternatives that will be developed in the coming weeks.

This week PBOT also finalized an updated detour plan that will be posted in the field and direct drivers to use Fairmount Blvd (West) to detour around the slide area closure. Additionally, in response to reports of barricades and signs at the slide closure being moved, PBOT reinforced both sides of the slide area with concrete blocks and secured metal barricades to prevent unwanted adjustments.

March 25, 2026

PBOT surveyors are completing field survey at the landslide site. Exploratory borings to collect soil data will occur the week of 3/30/26. Signed closures remain in place, and a map of area closures has been added to the project website.

March 19, 2026

Portland Bureau of Transportation (PBOT) surveyors are collecting field survey data at the landslide site. Contractors hired by BES will begin exploratory borings to collect soil data shortly. A signed detour route is in place and will likely be in effect into the summer months. The detour route will be added to the project website shortly.

 

Background

On Thursday, March 12, a landslide following heavy rains forced the closure of SW Fairmount Blvd. PBOT responded by closing the affected section of Fairmount Blvd to traffic and putting a signed detour in place.

Map

Closure area on SW Fairmount Blvd, in response to a landslide.

Contact

PBOT Customer Service (by PDX 311)

311Information and customer service
503-823-4000Every day, 7 a.m. to 8 p.m. (excluding federal holidays) Interpretation available | Interpretación disponible | Phiên dịch có sẵn | 提供口译服务 | Доступна интерпретация | Tafsiir la heli karo | Доступний переклад
711Oregon Relay Service

Follow on social media

Back to top