Transportation
Under Construction
This Local Improvement District (LID) project includes improvements to SW 47th Avenue from SW Luradel Street north to the deadend.
Construction from March 2021 through early May 2021
Location Description
SW 47th Avenue north of SW Luradel St.
Businesses Affected
0
Residences Affected
120
Project Background
City Council formed the LID on January 25, 2017. 100% design was completed on 10/30/19 with the start of construction pending on March 12, 2021.
Street includes:
- SW 47th Avenue from SW Luradel Street north to deadend.
Project Funding
Property owners are funding this project with overhead costs funded by the Portland Bureau of Transportation.