Sidewalk Infill: SE Washington St: 80th-82nd

Transportation
Engineering And Design
The Portland Bureau of Transportation (PBOT) is infilling sidewalk along the south side of SE Washington St from SE 80th Ave to 82nd Ave and closure of several driveways. The project is funded by Fixing Our Streets and Civil Rights Education and Enforcement Center (CREEC).
Example of previous PBOT sidewalk infill project on SE Ramona
Construction scheduled for late summer/early fall 2024.
Businesses Affected
2

What’s happening now?

(Updated Sep 2023) This project is in the design phase which began in March 2023. The project is wrapping up 60% design phase and conducting outreach to the impacted businesses.

Project Background 

This project includes construction along the south side of SE Washington Street from SE 80th Ave to 82nd Ave.  The project will construct curb-tight sidewalk, remove the existing temporary transit platform, update 3 ramps to be ADA-compliant, build a curb extension at the NE corner of 80th and SE Washington, mark a crosswalk at the east leg of 80th & Washington, and close several driveways on SE Washington Street.

Sign up for email updates

Get the latest updates about this project

Project Funding

This project is funded $600,000 from Fixing Our Streets and $275,000 from Civil Rights Education and Enforcement Center (CREEC). The Fixing Our Streets $0.10 per gallon fuel tax was approved by voters in May 2016 and again in May 2020. Due to a settlement with CREEC, PBOT has an agreement to deliver 1,500 ADA-compliant curb ramps per year for 12 years.