What’s happening now?
The project is complete.
Last Updated July 21, 2026.
Project Design
The project installed a sidewalk on the north side of SE Woodward Street between SE 57th Avenue and SE 58th Avenue. This provided a continuous sidewalk on the north side of SE Woodward Street between SE 52nd Avenue and SE 58th Avenue.
Project Background
Portland Bureau of Transportation's Safe Routes to School (SRTS) program conducted outreach in 2017 with Portland Public Schools and their communities to determine future projects according to highest safety need. SE Woodward was identified as a key street for students walking and rolling to and from Franklin High School. The segment of SE Woodward between SE 57th and SE 58th Avenues was identified as a sidewalk gap. You can learn more about the SRTS outreach process and see the SRTS Infrastructure Plan here.
Project Timeline
Project Development: January- May 2025
Project Design: June- November 2025
Construction: June- July 2026
Public Involvement
April 2026- Construction notification postcards mailed to the neighborhood
June 2025- Project notification postcards mailed to the neighborhood
Project Impacts
The project removed one tree adjacent to Clinton City Park in order to build the new concrete sidewalk.
Project Funding
This project was funded with a $80,000 budget from Fixing Our Streets.