What’s happening now?
Construction is expected to occur in May/June 2026 when the conditions are less wet and cold.
Last Updated April 2026
Project Description
The project will design and construct a sidewalk on the north side of SE Thorburn Street to create a safer and accessible sidewalk. The project will connect the new sidewalk to existing sidewalk near SE 73rd Avenue.
The project design includes the following elements:
- Approximately 355 feet of 7-foot wide sidewalk, and some sections with 5-foot wide sidewalk to preserve existing street trees
- Three new curb ramps at the intersection of SE 74th Avenue
This project has coordinated with the Jade and Montavilla Multimodal Improvement Project.
Project Goals
- Create an accessible pedestrian path on the north side of SE Thorburn Street
- Preserve the existing trees and shrubs with the sidewalk design
Project Impacts
- PBOT will be closing the north-south crossing on the east side of SE 74th Avenue at SE Thorburn Street
Project Background
This sidewalk project is a high priority sidewalk project in PedPDX, the citywide pedestrian master plan. Portland has over 170 miles of missing sidewalk across the city.
Project Timeline
Project Development: Summer 2024
Design: Summer 2024- Winter 2025
Construction: May/June 2026
Public Outreach and Involvement
April 2026
- Postcards: Construction notification postcards sent to the surrounding neighborhood
October 2024
- Letters: Letters sent to impacted property owners with the project design, explaining what they can expect to happen during construction.
Postcards: Project notification postcards sent to the surrounding neighborhood and neighborhood association.
Project Funding
This project is funded by general transportation revenue House Bill 2017 with a budget of $371,000.