Project Background
The Portland Bureau of Transportation is pleased to announce the successful completion of the award-winning NW Thurman St. Bridge Rehabilitation Project.
The 110 year-old Balch Gulch Bridge was built during the 1905 Lewis and Clark Centennial Exposition and World’s Trade Fair as a gateway to Portland’s developing Willamette Heights neighborhood. As the oldest intact bridge in the region and one of only few remaining of its type in the entire nation, the pin-connected steel deck truss is a noteworthy historic and engineering treasure. In fact, Dr. Robert Hadlow, Oregon Department of Transportation Historian, espoused the bridge as “one of the most significant spans in Oregon.”
Project Need
Structural deck elements like wood stringers and deteriorating steel floor beams caused many potholes and cracks along the bridge deck surface, making for an unsafe and uncomfortable ride. Furthermore, because of the imposed weight restriction, fire trucks were unable to use the aging bridge and were forced to make a one mile long detour which added four minutes to their response time in the area. Additionally, TriMet public buses were forced to reduce their speed while crossing the bridge to preserve its serviceable life.
Project Scope
Considering the age of the bridge and its poor condition, it would have been so easy to replace it with a shiny new one. However the easy path was not chosen. Given its unique characteristics, its special place in Portland history, and its eligibility for the National Register of Historic Places, rehabilitation of the Balch Gulch Bridge was really the only viable option.
Federal-aid funds were sought and obtained to rehabilitate the bridge by replacing all components above the historic deck trusses. After a local agency match, the total project budget was approximately $4 million.
In order to adequately address the bridge deficiencies, replacement of all components above the trusses was required. This meant the bridge had to be stripped down to its bones and rebuilt; a process that required equal amounts of technical merit and caution.
The historic handmade and antique bridge was lovingly restored with a new sidewalk, deck, and rail system. The riveted steel beams were replaced with modern replica versions. As a result, the weight restriction was lifted from the 110-year old bridge, the oldest intact span in Oregon.
Goals Accomplished
The decision to preserve the historic bridge inspired the public and government agencies alike. It also inspired PBOT to set the following goals:
- Lift the weight restriction without replacing the historic trusses
- Rehabilitate the bridge’s deteriorated superstructure while maintaining and honoring the historic aesthetics of the bridge
- Restore the original appearance of the 1905 historic bridge handrail, but strengthen it to meet modern safety standards
- Design the modern steel floor beams to match the shape of the deteriorated historic riveted steel beams
- Replace the deteriorated wood deck and riveted steel beams, while shoring the historic trusses in place
- Ensure that Lower Macleay Park remains open to the public during construction
- Keep the public constantly informed of progress by holding meetings, establishing a telephone hotline, creating a project website and publishing monthly newsletters
Awards
The success of the project has been recognized outside of PBOT. It has earned the following awards:
- American Public Works Association - National Project of the Year (Historical Preservation)
- Oregon Heritage Commission - Heritage Excellence Award
- American Public Works Association, Oregon Chapter - Project of the Year (Historical Preservation)
- ODOT Geo-Environmental - Professional Partnership Award
Read theproject celebration news release here.