See something we could improve on this page? Give website feedback.
Project Description
Installing permanent improvements at the following neighborhood greenway intersections
- NE 112th Street & NE Fremont Court
- Poured concrete islands and pavement markings
- NE 92nd Avenue & NE Tillamook Street
- Poured concrete islands and pavement markings
- NE 52nd Avenue & NE Alberta Street
- Poured concrete islands
- SW Illinois Street & SW 45th Avenue
- Poured concrete islands and pavement markings
- NE 53rd Avenue & NE Irving Street
- Poured concrete islands
- N Concord Avenue & N Killingsworth Street
- Poured concrete islands
Completed improvements:
- SE Salmon Street at 11th Avenue, 12th Avenue, SE 20th and 30th Avenue
- SE 11th Avenue: crosswalks and cross bikes
- SE 12th Avenue: crosswalks and cross bikes, concrete separators
- SE 20th Avenue: parking setback, left-turn calming rubber bumps
- SE 30th Avenue: crosswalks, cross bikes, and parking setbacks. Installing speed bumps on SE 30th Avenue in each direction of SE Salmon Street.
Project Goals
- Replace temporary infrastructure with more resilient permanent materials.
- Increase awareness for people entering a neighborhood greenway from a busier street.
- Improve crossing opportunities for people walking and rolling on select neighborhood greenways.
What's Happening Now
Updated 11/10/26
- Final designs for remaining locations have been signed and PBOT is working to procure a contractor. Concept designs are shown below.
- Onboarding contractor to install additional speed cushions on SE 30th between SE Belmont and SE Hawthorne to support safer operations of the SE Salmon neighborhood greenway crossing.
- Left turn calming devices on SE Salmon at the SE 30th and SE 20th intersections are awaiting construction by PBOT Maintenance Operations staff.
NE 112th Street and & NE Fremont Court Preliminary Design
NE 92nd Avenue & NE Tillamook Street Preliminary Design
NE 52nd Avenue & NE Alberta Street Preliminary Design
SW Illinois Street at SW 45th Avenue
NE 53rd Avenue & NE Irving Street Preliminary Design
N Concord Avenue & Killingsworth Street Draft Concept
Project Background
From 2020 to 2024, PBOT's "Slow Streets" program adding temporary traffic calming infrastructure along the neighborhood greenway network. The Fixing Our Streets program includes funding to replace temporary materials with permanent infrastructure.
Project Timeline
Summer 2025: Design
Fall 2025: Public Outreach - Letters sent to residents, businesses, and property owners in vicinity of improvements
Fall 2025: Construction SE Salmon Street at SE 11th, 12th, and 20th, and 30th Avenues
Fall 2026/Winter 2027: Construction at remaining locations
Public Outreach and Involvement
Fall/Winter 2025
Letters: Project notification letters sent to immediately adjacent properties, residents, and businesses
Presentation to the Buckman Community Association November 2025:
Project Funding
This project is funded by the Fixing Our Streets program.
Map
SE Salmon Street at 11th Avenue, 12th Avenue, SE 20th and 30th AvenueNE 112th Street and & NE Fremont Court
NE 92nd Avenue & NE Tillamook Street
SE 52nd Avenue & SE Alberta Street
SW Illinois Street at SW 45th Avenue
NE 53rd Avenue & NE Irving Street