What’s happening now?
The first phase of construction is underway. Expect heavy equipment and delays when traveling on NE 97th Avenue between Burnside and Glisan streets. Local access will remain open for businesses and residents unless otherwise notified.
The second phase of construction will start in Spring 2025; we are in the process of selecting a construction contractor via a low-bid solicitation.
Project Background
Portland City Council formed these LIDs on April 24, 2019. The project scope includes street, sidewalk, stormwater, and rail improvements.
Project Components
First phase:
- Extension of NE Davis Street from 97th to 99th avenues
- Repave NE 97th Avenue from Burnside to Davis streets
- Rebuilt traffic signal on E Burnside Street at 97th Avenue (includes crosswalks on all sides)
- New crosswalk on E Burnside Street east of 94th Avenue serving the I-205 multiuse path
- Improved angle of approach for people biking westbound on E Burnside Street across rail tracks
- New and rebuilt sidewalks, corner ramps, and streetlights throughout project area
- 43 new street trees with two-year establishment period
- 50 rail ties to be replaced near intersection of NE 97th Avenue & Burnside Street
Second phase:
- New street segments including sidewalks, corner ramps, and streetlights:
- NE Couch Street from 97th to 99th avenues
- NE Davis Street from 99th to 100th avenues
- 35 new street trees with two-year establishment period
Project Funding
Property owners are providing funding for this $15 million project with tax increment financing from the Gateway Urban Renewal Area, transportation system development charge (TSDC) funding and overhead costs funded by the Portland Bureau of Transportation.
Planning Documents
Contact project manager for plan details