See something we could improve on this page? Give website feedback.
What’s happening now and what to expect in the next two years?
July 2026 Update:
Following the successful second weekend closure of Lombard Street in early July, the contractor began bridge demo under the Lombard St. See photo below.
There will be other weekend closures of Lombard in the future and PBOT will be communicating with the public once we have a definite date of the closures. In the meantime, the contractor will continue working on the bridge within the working area.
NE Lombard Street has been reduced to one lane in each direction for the duration of the bridge construction (see cross section and layout below for reference).
PBOT will continue to update the project website and issue traffic advisories in advance of each scheduled weekend closure.
Please stay tuned for future updates.
Background
The current bridge over NE Lombard Street is on a recommended Emergency Transportation Route but is vulnerable to earthquakes. Freight uses the bridge as a connection between NE Lombard Street and Columbia Boulevard, but the current bridge's height and weight restrictions limit freight transportation. In addition, the current bridge does not have enough room for pedestrians and people biking. This new connection would fill the gap between the Holman Neighborhood Greenway and the protected bikeway on NE 47th Avenue. When it's complete, the bridge will provide better access for freight, pedestrians, and people biking.
The new bridge approaching from the north: a 6-foot wide buffered bike lane to the left, a 13-foot wide traffic lane in each direction, and a 10-foot wide multiuse path to the right.
The new bridge will have a cross-section of 7-foot wide elevated bike lane on the left, 13-foot wide traffic lane in both directions, and a 10-foot wide multiuse path on the right side of the bridge.
The new bridge approaching from the south: a 7-foot wide bike lane to the left, with a 3-foot buffer, a 13-foot wide traffic lane in each direction, and a 12-foot wide multiuse path to the right.
Funding
$25 million
The project has several funding sources:
- Build Portland
- HB 2017
- SDC
- HVUT
- General Funds
- ODOT
- Portland Clean Energy Community Benefits Fund (PCEF)
Sign up for email updates
Sign up for email updates on the NE 42nd Avenue Bridge project








