informational alert
Some city workers are on strike

The City of Portland Professional Workers, which represents 800 of the city's 7,500 employees, began a strike Nov. 9. Find the latest information about impacts to city services at Portland.gov/Strike.

informational alert
Portland is a Sanctuary City

NE 42nd Avenue Bridge Replacement (over Lombard Street)

Label: Transportation
Label: Engineering and design
The Portland Bureau of Transportation (PBOT) is constructing a new earthquake-ready bridge to provide better access for freight, pedestrians, and people biking. Bridge will fill the gap between the Holman Neighborhood Greenway and the NE 47th Avenue protected bikeway.
Construction will last approximately two years (2026 and 2027)

What’s happening now and what to expect in the next two years?

October 2026 Update:

Following the successful two weekend closures under the Union Pacific Railroad (UPRR) and Lombard Street (US Hwy 30) this summer, the contractor completed the demolition of the 42nd Bridge. See photo below.

Currently, the contractor is constructing the access road on the north side of the bridge to facilitate installation of the equipment needed for the retaining walls and bridge foundation shafts. Retaining wall backfill and foundation will also continue on the south side of the bridge. Once excavation of walls is completed they will move on with drilling. This work can be completed without closures to UPRR or Lombard Street.

Additional weekend closures of Lombard Street will be required in the future to accommodate bridge erection activities. PBOT will provide advance notice and communicate closure dates to the public once they have been finalized. In the meantime, the contractor will continue bridge construction activities within the designated work area.

NE Lombard Street has been reduced to one lane in each direction for the duration of the bridge construction (see cross section and layout below for reference).

 

 

PBOT will continue to update the project website and issue traffic advisories in advance of each scheduled weekend closure.

Please stay tuned for future updates.

 

Rendering of the replacement bridge on NE 42nd Avenue, pictured here in a cross-section over Lombard Street and the railroad.

Background

The current bridge over NE Lombard Street is on a recommended Emergency Transportation Route but is vulnerable to earthquakes. Freight uses the bridge as a connection between NE Lombard Street and Columbia Boulevard, but the current bridge's height and weight restrictions limit freight transportation. In addition, the current bridge does not have enough room for pedestrians and people biking. This new connection would fill the gap between the Holman Neighborhood Greenway and the protected bikeway on NE 47th Avenue. When it's complete, the bridge will provide better access for freight, pedestrians, and people biking.  

The new bridge approaching from the north: a 6-foot wide buffered bike lane to the left, a 13-foot wide traffic lane in each direction, and a 10-foot wide multiuse path to the right.

The new bridge will have a cross-section of 7-foot wide elevated bike lane on the left, 13-foot wide traffic lane in both directions, and a 10-foot wide multiuse path on the right side of the bridge.

 

The new bridge approaching from the south: a 7-foot wide bike lane to the left, with a 3-foot buffer, a 13-foot wide traffic lane in each direction, and a 12-foot wide multiuse path to the right.

 

Overhead view of NE 42nd Avenue Bridge over Lombard Street and freight traffic.

Funding

$25 million

The project has several funding sources:

  • Build Portland
  • HB 2017
  • SDC
  • HVUT
  • General Funds
  • ODOT
  • Portland Clean Energy Community Benefits Fund (PCEF)
     

Sign up for email updates

Sign up for email updates on the NE 42nd Avenue Bridge project

Map

NE 42nd Avenue Bridge Replacement
Back to top