What's happening now?
- The construction contractor is actively working on installing signing and striping on the greenway.
What's the project scope?
N Killingsworth to N Kilpatrick Street
19 speed bumps. Delaware greenway is using speed bumps because the majority of the corridor is under 32” wide.
N Killingsworth Street at N Delaware Ave
Stripe green ‘crossbikes’ and stripe crosswalk on east leg of intersection
N Rosa Parks Ave at N Delaware Ave (complete)
Stripe green ‘bike box’ to separate people biking from people driving at red light. Right turns will not be permitted on red lights for people driving in order to prevent crashes. On-street parking removal adjacent to bike boxes.
N Sumner Street to N Terry Street
Paint sharrows
Install wayfinding signs
Improve visibility as needed at intersections by pulling on-street parking back from corners
Turn stop signs as needed to favor continuous/un-stopped travel on Delaware Neighborhood Greenway
- Vehicle volumes are already low - no traffic diversion off of the greenway is planned.
- Note about N Lombard at N Delaware Ave: The crossing of Lombard at Delaware will continue to utilize the ODOT-built pedestrian crossing in the near term. PBOT will not have enough funding to make substantial changes to the N Delaware and N Lombard intersection at this time.
Stay involved
Sign up for email updates through GovDelivery:
Get the latest updates about this project.
View the postcard mailed to 4,000 area residents about the project in June 2023:
Learn more about future North Portland biking and walking projects
PBOT's North Portland in Motion is a two-year planning effort to identify transportation needs and investments to improve access to community destinations and support walking, biking, and transit use in the North Portland peninsula.