What’s happening now?
Construction is mostly complete. The traffic diverter at SE 50th and Lincoln will be replaced by a permanent diverter design.
Project Background
Read the complete background on this project.
Portland’s 2015 Neighborhood Greenway Assessment Report identified this greenway as one of the city’s five worst-performing because of its stretches of high traffic volumes and speeds.
The majority of the Lincoln-Harrison Neighborhood Greenway receives over 1,500 vehicles a day—and many sections see over 2,000 vehicles a day, or double the recommended amount. Vehicle speeds are also a concern on this neighborhood greenway.
The city is addressing the speed and volume issues as part of its strategy to build a network of ‘low-stress’ bikeways. Research shows that ‘low-stress’ bikeways that feel safe and comfortable attract new riders.
Project Components
PBOT staff evaluated project components based on their ability to reduce vehicle volumes and speed, their feasibility, and their cost. Project elements were modified to reduce out-of-direction travel for local residents. The map below includes revisions PBOT has made as a result of resident feedback:
Speed reduction for SE 50th
As the result of a neighborhood resident investigation request, the speed zone on SE 50th Ave from SE Powell Boulevard to SE Hawthorne Boulevard will be reduced from 35 miles per hour to 30 miles per hour.
30th and Harrison-Lincoln crosswalk
In response to community feedback, PBOT has modified the design of the crosswalk’s southwest corner to further tighten the intersection and provide shorter crossings for pedestrians.
Diversion at 50th and Lincoln
Lowering the number of vehicles on the neighborhood greenway may mean changes to your route home or on your street. We are making this change (and changes like it around the city) to attract new people to travel by bicycle in Portland. By attracting new people to travel by bicycle, the city can reduce greenhouse gas emissions and manage the growth Portland is experiencing and will continue to experience.
We explored multiple ways to address vehicle volumes and speed east of Cesar Chavez before selecting traffic diversion. We evaluated a range of potential project elements based on their ability to reduce vehicle volumes, as well as their effectiveness, feasibility, and cost.
Evaluating traffic diverter success
1. Did diversion reduce car volumes on Lincoln to acceptable levels?
An acceptable level means that car volumes both east and west of 50th are below 1,500 vehicles per day, with less than 75 vehicles per hour in the peak direction. This level comes from Portland’s Neighborhood Greenways Assessment Report, which set guidelines for the city’s neighborhood greenways:
- Greenways should be designed, built, and maintained for an average of 1,000 vehicles a day or 50 vehicles per hour in the peak direction.
- While not ideal, a greenway can operate with an average of 1,500 vehicles per day or 75 vehicles per hour in the peak hour.
- Greenways should be improved or maintained to not exceed an average of 2,000 vehicles a day or 100 vehicles per hour in the peak travel direction.
If the diverter does not result in acceptable volume reductions, additional diversion may be necessary. An alternative may be a diverter at 60th to prevent westbound auto traffic yet allows transit access.
2. Did traffic diversion from Lincoln create unacceptable conditions on nearby streets?
Portland’s Neighborhood Greenways Assessment Report also set guidelines for local service streets near neighborhood greenway traffic calming efforts. As a result of a traffic calming project on a neighborhood greenway, traffic volumes on adjacent local service streets should not exceed 1,000 cars per day or 50 cars per hour during peak demand. If a side street has post-project vehicle volumes above 1,000 daily trips or 50 cars per hour during peak demand and it did not have a pre-project volume problem, we will do follow-up counts to confirm the change is not random and propose mitigation.
Potential mitigation tools
Common mitigation includes adjusting stop signs, traffic calming on the secondary street, diversion on a secondary street, or modification of the primary greenway project.
Previous examples of mitigation in Portland
Stop signs reoriented on SE Ash at 13th, 15th, and 18th and on SE Pine at 15th, 16th, and 18th south of the diagonal diverter at SE 15th and Ankeny to create a stop plan and reduce incentive to cut through the neighborhood (SE Ankeny Neighborhood Greenway).
Speed bumps installed on SE Woodward between SE 26th and Caesar Chavez Blvd south of the diverter at 32nd and Clinton to discourage non-local traffic use and reduce speeds (Clinton Neighborhood Greenway).
A second diverter installed on N Mississippi at Holman to reduce diversion from Michigan at Rosa Parks Way median barrier (Michigan Ave. Neighborhood Greenway).
Public Involvement
Residents provided feedback to PBOT staff at two open houses, an online survey, three neighborhood association meetings, and other communication channels in 2017. Based on resident feedback, we have made changes to the originally proposed project.
- We heard that access from 50th is a concern for many neighborhood residents living nearby. The new median diversion design allows residents to connect to Lincoln from 50th. The new design restores right turns from 50th onto Lincoln.
- A previously proposed design only allowed for vehicles to exit Lincoln onto 50th in either direction. The design has changed from no turns onto Lincoln from 50th, to some turns onto Lincoln from 50th.
- We heard concerns about where the traffic diverted from 50th and Lincoln will go. We will first be installing a low-cost interim median diverter. This will allow us to speed up the process of collecting traffic data to verify the expected impacts on neighboring streets. This analysis will be shared online. Based on the results of this data, we will look at mitigation in line with our traffic calming policies.
- We heard concerns that the diversion at 50th would add additional stress to Hawthorne between 50th and 60th, which already feels unsafe to nearby residents. We will install traffic calming measures on Hawthorne between 50th and 60th to slow this corridor.
- We heard that vehicles crossing the neighborhood greenway unsafely are a concern for pedestrians and bikers. PBOT is also concerned about unsafe crossing and driving behavior. We are working to identify appropriate treatments that can contribute to safer and more comfortable neighborhood greenways.
- We heard concerns that traffic diversion near 30th and Lincoln, 26th and Lincoln, and 50th and Lincoln diverters will create unsafe vehicle volumes and speeds on nearby streets. Similar installations have been successful at evenly distributing displaced traffic, but each corridor is a unique case. Six months after their installations, we will evaluate vehicle volumes and speeds on streets near the new diverters. Based on the results of this data, we will look at mitigation in line with our traffic calming policies.
Sign up for email updates
Get the latest updates on this project
Question and Answer (Q+A)
1. Why more space for people using bikes?
It is in everyone’s best interest to reduce dependency on single occupant auto trips.
- Congestion
PBOT is responsible for helping all residents of Portland move about the city. With an expected 130k+ increase (+20%) in population over the next 20 years, it is unlikely residents will be willing to tear down homes to widen roads for everyone to be able to drive. Providing alternatives to driving will be key to reducing maintenance costs and congestion in the future. Neighborhood Greenways, like SE Lincoln, are part of the solution to reducing future congestion by enabling those that want to use a bike to comfortably travel about the city instead of a car. It is in everyone’s best interest to reduce dependency on single occupant auto trips. See: Transportation System Plan introduction (found in 2007 TSP documents)
- Pollution
Portland has an adopted strategy to reduce greenhouse gas emissions. Helping residents to safely walk, bike and use transit for a variety of trip lengths means fewer cars emitting pollution to move the same, or more, people around our city.
- Safety
PBOT is changing the way it looks at road safety. The traditional method of only spending taxes where crashes have occurred in the past means we will always be chasing problems. Vision Zero refocuses efforts toward finding solutions for common problems and systemically applying those solutions to prevent future crashes from occurring. Examples of this include:
- Pedestrian medians in center turn lanes.
- Signals along school routes getting protected lefts.
- All signals getting protected left turns.
- Modern roundabouts at high crash intersections.
- New crosswalk upgrade standards.
- Community Health
City Council adopted the Portland Plan in 2012 as a road map on how to improve all aspects of Portland. It includes goals to improve the health of Portland residents, and the exercise and improved safety greenways offer are part of that goal.
2. What is a Neighborhood Greenway?
A Neighborhood Greenway is the label PBOT uses for a system of local auto streets for cyclists to use as collector streets that parallel busier arterial auto streets. Many cyclists do not feel comfortable riding on the busier auto streets and Neighborhood Greenways give cyclists through streets in the same way arterials streets serve such needs of motorists. The ideal goal is to create linear park-like environments for walking and biking. The roadways are intended to be shared by people driving cars and people riding bikes. Safety of cyclists is prioritized on Neighborhood Greenways because of the shared environment. To encourage use by people riding bikes, an ideal goal of 1,000 auto trips per day, with a maximum of 2,000 per day, along with 85th percentile auto speeds of 17-23 mph are the target metrics.
3. What is the 1,000 vehicles per day related to?
As part of its assessment of Neighborhood Greenways PBOT identified a set of traffic volumes as measurements of success. 1,000 auto trips per day was established as the ideal goal for the number of cars daily using a street that families would be encouraged to use by bike. The 1,000 auto trips per day standard is about the same as cyclists being passed by a car less than once a minute. When an existing or proposed greenway route has a car volume below 1,000 vehicles per day, no diversion of auto traffic will be proposed. When a proposed greenway route has more than 1,500 auto trips per day, diversion may be considered. If auto volumes on a proposed greenway exceed 2,000 per day, diversion of auto traffic shall be considered.
4. Will my side street see more traffic because of the project?
Many greenways are traditional through streets in a neighborhood, even though their designation is the same as the other nearby streets. The reasons one street is used more than others often involves fewer stop signs along that path, or the presence of signals at crossings of higher order roadways, both of which attract users. Diversion on a greenway redistributes local traffic amongst the local streets so all the local streets in a neighborhood share the load more evenly, and it is expected that the total volume of through traffic in a neighborhood will go down after diversion is implemented. Diversion along a greenway is expected to move traffic to other nearby streets. Since diversion on Neighborhood Greenways was adopted as part of the Neighborhood Greenways assessment report, a maximum threshold was established for side streets near the greenway to reduce the impact to adjacent residents. Since 1,000 car trips per day was the chosen ideal volume for bike use, this number is also used as the permitted maximum volume on any adjacent side street as a result of a project. This is not an increase of 1,000 cars per day, but a total post-project volume. So, if your street only has 300 current daily trips, it could see another 700. But if your street already has 800 daily trips, the available space is only 200 more daily trips. PBOT uses pre-project counts to help decide where to place diversion, preferring to place it where there is more capacity to absorb diverted drivers.
5. What happens if my side street ends up with more than 1,000 daily trips after the project?
PBOT takes numerous counts away from the project street to gauge the effects of the project on the nearby local streets. If a side street has a post project volume above 1,000 daily trips, and it did not have a pre-project volume problem, PBOT will do follow-up counts to confirm the change is not random, and propose mitigation should a problem remain. The most common mitigation is adjustment of stop signs, traffic calming on the secondary street, diversion on a secondary street and modification of the primary greenway project.
6. What if I live on a side street that already has too much traffic?
The focus of a Neighborhood Greenway project is the greenway. PBOT can review other issues in a neighborhood that may be related to the operation of the greenway, but will focus greenway resources on improving the greenway to encourage bike use along that path. Other traffic concerns should be directed to (503) 823-SAFE.
7. I don’t like speed bumps. Can we have more diverters?
PBOT has had good success with speed bumps over the years. Speed bumps are the most effective tool to slow speeding auto traffic. It has been suggested that more diverters, maybe every ¼ mile (about every 5 blocks) would do the trick. PBOT’s experience shows that 5 blocks are enough distance for people driving to accelerate faster than 25 or 30 mph. PBOT can, sometimes, phase in bumps in groups, measuring to see if diverters alone are doing the job, but it is uncommon that this works.
PBOT has experimented with fire truck friendly speed bumps and continues to explore ways to slow speeding motorists with minimum delay to people biking.
8. I don’t like diverters. Why can’t we have just speed bumps and signs?
Speed bumps are the most effective tool to reduce speeding drivers, but PBOT has a goal of also reducing the number of cars along a greenway so that families feel comfortable riding around. PBOT has had mixed results affecting traffic volume using just bumps, so does not rely on them to reduce traffic volume. Traffic engineers also have a saying: “If signs fixed things, you wouldn’t need traffic engineers”. Any regulatory sign requires regular and random enforcement presence to be effective. Such presence is not predictable and is also expensive.
9. What about Emergency Vehicle Access?
PBOT works closely with Portland Fire and Rescue (PF&R) to minimize delay for fire response. As part of joint testing efforts, the largest and heaviest fire trucks were found to be the most affected by speed bumps and traffic circles. Almost all diverters proposed will be designed so that a fire truck can drive over, or past, the diverter along a similar path the driver would normally take, and all proposed diversion is reviewed by PF&R. PBOT and PF&R have also worked over the years to develop a major and secondary response route network to minimize delay on the pathways fire trucks use the most. New traffic calming and diversion are not permitted on major response routes and only fire friendly speed cushions are permitted on secondary response routes.
Lincoln Greenway Questions
1. Why Harrison-Lincoln? Aren’t there other streets with greater needs?
Traditionally, PBOT has modified a street for livability concerns and moved on. It has been uncommon for PBOT to go back to a street and upgrade to current standards, even when those standards are significantly different than with the original project. In 2015, PBOT initiated an assessment of all greenways, formerly called bike boulevards, to get a snapshot of how the streets were performing for cyclists, based on the draft metrics developed in 2009. The assessment report identified six former bicycle boulevards (legacy greenways) that carried a significant amount of bike traffic, and had high car volumes and speeds. These legacy greenways included:
• NE Alameda
• SE Ankeny
• SE Clinton-Woodward
• SE Lincoln-Harrison-Ladd
• NW Greenways, and
• NE Tillamook
SE Clinton, 12th to 50th, is complete, and SE Ankeny, 12th to 28th, is pending completion. NE Tillamook was to be next, but a Bureau of Environmental Services project in the west end would have conflicted with the greenway project. NW in Motion is in the planning stages, which leaves Lincoln-Harrison-Ladd and Alameda as the remaining legacy greenways identified for future upgrades.
To be sure, there are many parts of Portland with bike infrastructure needs, and PBOT is currently pursuing over a half dozen ‘new’ greenways east of 82nd Avenue, as well as continuing to identify missing links in the current system and plan enhancements on other legacy greenways.
2. Why is Harrison becoming a collector street?
SE Harrison, 26th to 30th, as well as 26th south of Harrison and 30th north of Harrison are already designated as Neighborhood Collector streets in Portland’s Transportation System Plan (TSP). The Harrison-Lincoln Greenway project is not changing any traffic classifications.
The purpose of Neighborhood Collector traffic streets is to provide a connection between lower classified Local Service streets and higher classified streets. The TSP does not define traffic streets by how much traffic uses them, since cities grow and shrink, but instead on the function they are meant to serve for a variety of modes. Portland has Neighborhood Collectors with hundreds of car trips daily and a few with thousands of car trips daily. It all depends on where the collector is and nearby land uses.
The next higher classification, District Collector, are the streets meant for traffic moving between districts in the city and meant to serve through traffic over longer distances. SE Hawthorne west of 50th is a District Collector.
3. Why only three diverters?
PBOT is still evaluating the effectiveness of diversion internal to a Neighborhood Greenway. PBOT has traditionally only placed diverters at major cross-streets. Internal diversion creates more inconvenience for residents inside the local area, and PBOT is expanding its knowledge about how different forms of diversion interact with neighborhood traffic patterns. On SE Clinton, 12th to 50th, two new diverters were added to the two existing semi-diverters at Chavez, bringing the total to four along a 2-mile corridor. The results on SE Clinton have been better than expected. The SE Ladd/Harrison/Lincoln corridor is three miles long and four new diverters are proposed to be added to the existing three, for a total of seven diverters.
4. How did diversion affect streets along the Clinton Greenway?
Area side streets near Clinton were monitored in the same way as streets near Harrison-Lincoln. After the two new diverters were installed, PBOT measured one block of one street, SE Woodward, that exceeded the 1,000 trips per day standard. PBOT provided traffic calming between 26th and Chavez to mitigate for that traffic increase. Post project counts on SE Woodward have been reduced to acceptable diversion standards. Traffic volume increases on other side streets ranged from reductions of over 100 daily trips to increases of up to 400 daily trips.
Additionally, auto use along Clinton has reduced by more than 30% (-900+ cars) while bike use has been similar or increased. The largest increases were measured west of 20th, exceeding a 30% increase in cyclists in May of 2016.
5. The diverters at 50th will only make things worse on side streets east of 50th.
Adding diversion on Lincoln at 50th changes how local residents can get to their homes, it does not eliminate access. From a general circulation perspective, not all residents from 50th to 60th, between Division and Hawthorne should be using Lincoln as their primary access point. Those closer to Hawthorne should be using Hawthorne, while those closer to Division should be using Division. Lincoln has the same designation as all the less busy side streets it crosses. For years now, residents living along Lincoln have had to deal with too much traffic on their Local Service street, while residents elsewhere in the neighborhood have benefited from this inequity.
As with any Neighborhood Greenway project, streets near the proposed diverters will be monitored for traffic increases. Like Woodward Street near the Clinton greenway, excessive diversion will be mitigated.
6. What about Emergency Vehicle Access?
PBOT works closely with Portland Fire and Rescue (PF&R) to minimize delay for fire response. As part of joint testing efforts, the largest and heaviest fire trucks were found to be the most affected by speed bumps and traffic circles. Almost all diverters proposed will be designed so that a fire truck can drive over, or past, the diverter along a similar path the driver would normally take, and all proposed diversion is reviewed by PF&R. PBOT and PF&R have also worked over the years to develop a major and secondary response route network to minimize delay on the pathways fire trucks use the most. New traffic calming and diversion are not permitted on major response routes and only fire friendly speed cushions are permitted on secondary response routes.
7. You’re blocking my access.
- Harrison between 20th and 30th has 26 current access points from higher order streets, and one is proposed for entry restriction.
- Lincoln between 30th and Chavez has 29 current access points, and one is proposed for entry restriction.
- Lincoln between Chavez and 50th has 32 current access points, and one is proposed for entry restriction.
- Lincoln between 50th and 60th has 16-18 current access points, and one is proposed for entry restriction.
Of the 103 current access points to the Harrison-Lincoln portion of the project, four access points (4%) are proposed for half closure. The longest extra distance for a local resident to travel to one of those access points is about ½ mile, and at 25 mph (33 feet per second) the extra time to do so would be about a minute and a half.